Draft Schedule for Run02-10, 2013

July 30th 0800 – July 31st 0800



Time

Descriptions

Studiers

SR Status


Tuesday, July 30, 2013



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Install fan control system in S3

Erwin

No Beam

0930-1030

test the upgrade of iocs40fb with beam

S. Xu

Stored beam

0930-1130

Replace RF5's control buffer card #7

RF Group

No Injection

0930-1100

Update Linac reference files

Pasky

Limited injection

1100-1200

Linac training

Pasky/Angel

Limited Injection

1200-1400

SCU0 quench test (using a beam dump) with ideal ID steering. 100 mA in 24 bunches.

Harkay

Stored beam & injection

1400-1500

test new SR scope configure for SR injection

Yao

Stored beam & injection

1500-1700

center BTS trajectory through the quads. booster beam and injection

Yao

Stored beam & injection

1700-2200

Reference lattice study

Emery

Stored beam & injection

2200-2400

high beta function study

Xiao

Stored beam & injection


Wednesday, July 31, 2013



2400-0200

high beta function study (continued)

Xiao

Stored beam & injection

0200-0700

continue 3NLSS lattice

Sajaev

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection