Machine Studies
Draft Schedule for Run02-2, 2013
June 4th 0800 - June 5th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, June 04, 2013 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Replace RTD at S11/12 vac skid |
Putnam |
No Beam |
0930-1030 |
Replace PAR bunch cleaning amplifier |
Gold, Yao |
No Injection |
0930-1130 |
Replace fan control system in Rack 38-04 |
Erwin |
No Beam |
0930-1030 |
Datapool IOC test |
Shang |
No beam |
0930-1330 |
Pull and phase match cables in Klystron gallery |
Diagnostics |
Stored beam and injection |
0930-1230 |
Troubleshoot B:SD |
Puttkammer |
No Injection |
0930-1230 |
Troubleshoot B:ES2 |
Deriy |
No Injection |
0930-1230 |
Troubleshoot S37 PS communications |
Fors |
No Beam |
0930-1200 |
TDR the cables for S27BP1 |
Erwin |
No beam |
0930-1200 |
RF waveguide switch and verification of Voodoo card repair at RF3 |
RF Group |
No beam |
0930-1030 |
Investigate Kalmus interface at RF2 |
Berenc |
No beam |
0930-1200 |
Replace VXI crate for S38 cavities |
Meyer |
No beam |
0930-1130 |
Replace RF2's TR Set pressure 6psi regulator |
Trento |
No beam |
0930-1000 |
Prepare for Zone B access |
Operations |
No beam |
1000-1100 |
Replace sector 23-24 Absorber interlock analog input card. |
Putnam |
No beam |
1000-1200 |
Troubleshoot 10-BM PSS |
Markovich/ Gagliano |
Access Zone B |
1030-1130 |
Replace S37Cav2US and Cav4DS IR detectors |
Morrison |
Access Zone F |
1230-1300 |
Recover SR after access |
Operations |
Stored beam & injection |
1230-1330 |
setup BTS with lower B:ES2 setpoint. |
Yao |
No beam |
1300-1800 |
Initial BPM checkout |
Decker |
Stored beam & injection |
1800-2000 |
IEX check-out |
Xiao |
Stored beam & injection |
2000-2400 |
CPU correction |
Xiao |
Stored beam & Occ. injection |
2000-2200 |
PAR training (15-23) |
Obasohan |
Limited Injection |
2300-2400 |
PAR training (23-07) - continued |
Oziemkowski |
Limited Injection |
|
Wednesday, June 05, 2013 |
|
|
0000-0100 |
CPU correction (continued) |
Xiao |
Stored beam & Occ. injection |
0000-0100 |
PAR training (23-07) - continued |
Oziemkowski |
Limited Injection |
0100-0300 |
Optimize injection |
Sajaev |
Stored beam & injection |
0300-0700 |
Accumulation limit measurement |
Sajaev |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |