Machine Studies

Draft Schedule for Run02-3, 2013

June 11th 0800 - June 12th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, June 11, 2013



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1030

Patch non production RTFB IOC

Arnold

Stored Beam & Injection

0930-1130

Investigate S33B:Q4 temperature readback

Puttkammer

No Beam

0930-1130

Troubleshoot L1 temperature trips

Horan

No Injection

0930-1130

Verify/compare that the CPU power supply is operating within specifications.

Puttkammer

No injection

0930-1030

Check power level at L3 DMU

Jefferson

No injection

0930-1130

hook up a scope and monitor SR sector 36 converter cabinet 3 Gespac power supply

Putkammer

No Beam

0930-1130

Remove the external diagnostics in BES2

Goetzen

No Injection

1000-1100

Replace iocs15fb MVME5100 CPU

Laird

No Beam

1200-1215

End to end test at 10BM

SI group

No Beam

1200-1230

Recover SR systems

OPS

Stored Beam & Injection

1230-1800

Continue CPU correction

Xiao

Stored Beam & Occ. Inj.

1230-1330

PAR training (07-15)

Obasohan

Limited Injection

1330-1600

check PAR extraction and scan kicker timing

Yao

Limited Injection

1600-1800

test a new PTB lattice

Sereno/Yao

Occ. Inj. possible

1800-2200

bpm commissioning, noise studies, and gap scans

Decker

Stored beam & inj.

2200-2400

Accumulation limit measurement

Sajaev

Stored beam & inj.


Wednesday, June 12, 2013



0000-0300

Accumulation limit measurement (continued)

Sajaev

Stored beam & inj.

0300-0700

APS-U lattice setup

Sajaev

Stored beam & inj.

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection