Draft Schedule for Run02-7, 2013

July 9th 0800 – July 10th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, July 9, 2013



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1000

Move PV gateway

Smith

No Beam

0930-1100

Install rack fan control system

Erwin

No Beam

0945-1000

Check 10BM shutter operation with automated script (will need shutter permit)

SI Group/10BM

No beam

1000-1100

Troubleshoot 14ID PSS fault

Banks

Access Zone B

1000-1030

Install 2 sensors to test for radiation effects with stored beam

RF Group

Access Zone F

1100-1130

Recover SR systems

OPS

Stored Beam & Injection

1130-1330

Measure chromaticity of 325MeV booster lattice

Yao

Stored beam & injection

1330-1400

Check response of S16C:P0

Schroeder

Stored beam

1400-1600

measure the SCU0 chamber alignment with the beam (ID scan)

Harkay

Stored beam & injection

1600-1800

collect data for optics correction study and chromaticity measurement via decoherence

Wang, C.

Limited injection

1800-2200

Orbit switch

Xiao

Stored beam & injection

2200-2400

continue CPU correction or High Beta Lattice

Xiao

Stored beam & injection


Wednesday, July 10, 2013



0000-0400

continue CPU correction or High Beta Lattice (continued)

Xiao

Stored beam & injection

0400-0630

OPEN



0630-0800

Prepare for User beam

OPS

Stored Beam & Injection