Machine Studies
Schedule for Run03-3, 2013
October 15th 0800 - October 16th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, October 15, 2013 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0930-0945 |
Switch PAR Fundamental RF systems |
RF Group |
No Injection |
0930-1000 |
Reboot interleaving DSPs |
PS Group |
No Injection |
0930-1130 |
PS script testing & investigate occasional on/Reset commands failing to reach converters |
Fors |
No Beam |
0930-1130 |
Inspect Linac modulator RTDs |
Cours |
No Injection |
0930-1130 |
Install valves for new PAR circulator |
Wright |
No Injection |
0930-1230 |
Characterize RF gun kickers |
Pasky |
No Injection |
0930-1130 |
Investigate why several L1 P.S. will shut off remotely |
Hillman |
No injection |
1000-1200 |
Replace RF cavity blowers in Booster |
Morrison |
Booster Access |
1000-1100 |
Switch from back-up to primary process water pump in S19/20 (P.S. in S18,19,20,21 off) |
Theres |
No beam |
1000-1200 |
Troubleshoot S1/2 process water pump trips which occurred last week (P.S. in S40,1,2,3 set to 0) |
Rohlfing/MOM group |
No beam |
1300-1500 |
SCU0 beam-based alignment. |
Harkay |
Stored Beam & Injection |
1300-1500 |
Injector training (09-15) (parallel to SCU0 BBA). |
Oobasohan |
Limited Injection |
1500-1700 |
Troubleshoot S27B:P0 and RTFB debugging |
Erwin/ Lenkszsus/ Sereno |
Stored Beam & Injection |
1700-2300 |
High charge booster beam study. Inject 324 bunches before starting. |
Yao Chae DiMonti |
No injection |
1700-2100 |
CPU setup (parallel to booster study). |
Xiao |
Stored Beam & Injection |
2100-2200 |
Reload BPLD limits if required. |
OPS |
No impact |
2300-2400 |
Injection into small aperture. |
Emery Sun |
Stored Beam & Injection |
|
Wednesday, October 16, 2013 |
|
|
0000-0300 |
Injection into small aperture (continued). |
Emery Sun |
Stored Beam & Injection |
0300-0700 |
Set up high betaX for hybrid operation. |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |