Machine Studies

Schedule for Run03-7, 2013

November 11th 0800 – November 13th 0800

Time

Descriptions

Studiers

SR Status

 

Monday, November 11, 2013

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/

OPS

Stored Beam & Injection

0930-1030

Test user operations PEM

Schroeder/ Shang

No Beam

0930-1030

Enter RF5 klystron garage to do some measurements.

Horan

No beam

0930-1130

PS script testing Zone C

Fors

No Beam

0930-1130

Investigate comm loss between iocs35das & iocs35fb

Lenkszus

No Beam

0930-1130

Check input transformer tap for BQD

Wang

Limited Injection

0930-1130

Move external monitors

Wang

No Beam

0930-1300

Install PAR RF12 circulator

RF Group

No Injection

0930-1730

Water tie in at S35BM

Wyncott

35BM offline

1000-1100

Troubleshoot xbpm at 34BMP1

Hahne

Zccess Zone E

1000-1300

Verify 35ID wiring / 35BM work

McNamara / Friedman

Access Zone F

1330-1430

Test RF PEMs

Schroeder / Soliday

No Beam

1330-1630

Verify klystron water readbacks

RF Group

Stored Beam & Injection

1430-1500

Recover SR beam.

OPS

Stored Beam & Injection

1500-1600

SR requalification.

Bogdan

Stored Beam & Injection

1600-1700

S27 orbit bump test for RTFB.

Sereno

Stored Beam & Injection

1700-2100

High-charge injector study.

Yao

Limited injection

2100-2400

Set up RHB lattice.

Sajaev

Stored Beam & Injection

 

Tuesday, November 12, 2013

 

 

0000-0100

Set up RHB lattice (continued).

Sajaev

Stored Beam & Injection

0100-0500

Orbit switch.

Xiao

Stored Beam & Injection

0500-0900

Test injection with high coupling.

Xiao

Stored Beam & Injection

0700-0900

Injector training if possible (parallel to high coupling injection).

Angel

Limited injection

0900-1100

FPGA optics correction test.

Wang

Stored Beam & Injection

0900-1100

Investigate Booster QD correction (parallel to FPGA).

Yao

Limited injection

1100-1900

Perform ID gap scans.

Sereno

Stored Beam & Injection

1900-2300

Xray BPM alignment.

Hahne

Stored Beam & Injection

2300-2400

Search for possible vertical aperture restriction in SR.

Emery

Stored Beam & Injection

 

Wednesday, November 13, 2013

 

 

0000-0300

Search for possible vertical aperture restrictions in SR (continued).

Emery

Stored Beam & Injection

0000-0200

Injector training (parallel to aperture search).

Obasohan

Limited Injection

0300-0700

Injection tune up software development.

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection