Machine Studies
Schedule for Run01-3, 2014
February 11th 0800 - February 12th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 11, 2014 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Switch PAR RF #1 systems |
RF Goup |
No Injection |
0930-1030 |
Troubleshoot iocrf5mon |
DiMonte |
No Beam |
0930-1030 |
Test medm script |
Bui |
No Beam |
0930-1130 |
Cathode emission tests on L4 & L5 |
RF Group |
No Injection |
0930-1030 |
Booster ramps supply test |
Yao/Shang |
No Booster beam |
0930-1130 |
Remove waveguide shorting plates |
RF group |
All 352Mhz RF off |
0930-1130 |
Waveguide switch from RF2 to RF3 |
RF Group |
No Beam |
1000-1100 |
Switch process water pumps S23-36 |
Wright |
No Beam |
1000-1100 |
Troubleshoot 10BM SS2 switch |
Banks |
Access Zone B |
1000-1100 |
Measure 10ID vacuum chamber |
Erwin |
Access Zone B |
1000-1100 |
Tune PID loops at S37 |
Erwin/FMS |
No Beam |
1130-1230 |
Adjust PTB current monitor |
Keane/Yao |
Limited Injection |
1230-1330 |
SR training |
Obasohan |
Stored beam & inj. |
1330-1430 |
Booster training (09-15) |
Angel |
Limited Injection |
1430-1700 |
RG1 beam studies |
Pasky |
Limited injection |
1430-1700 |
IEX check up with beam |
Xiao/Smith/Deriy |
Stored beam & occ. injection |
1700-1900 |
test 4 corrector/bpm bump for RTFB hardware test. Take more 12 second and 1 second FPGA bpm data sets. |
Sereno |
Stored beam & injection |
1900-2200 |
SCU0 BLM study |
Harkay/Dooling |
Stored beam & inj. |
2200-2400 |
vertical beamsize measurement with scraper |
Emery/Sajaev |
Stored beam & injection |
|
Wednesday, February 12, 2014 |
|
|
0000-0100 |
vertical beamsize measurement with scraper (continued) |
Emery/Sajaev |
Stored beam & injection |
0100-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |