Machine Studies
Draft Schedule for Run01-5, 2014
February 24 th 0800 – February 26th 0800
Time |
Descriptions |
Yao, Shang |
Limited injection |
|
Monday, February 24, 2014 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Run network monitoring |
Leibfritz |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving DSPs |
PS group |
No Injection |
0930-1000 |
RF waveguide switch from RF2 to RF3 |
RF Group |
No Beam |
10-1130 |
Determine if the S40 TC problem is a bad TC module on the PLC, or if it is a thermocouple issue in the tunne |
RF Group |
No beam |
1000-1030 |
Replace cable from to scope |
RF Group |
No Beam |
0930-1000 |
Reboot iocacis |
Ops |
No Beam |
0930-1130 |
Reboot FPGA bpms |
Pietryla |
No Beam |
1000-1100 |
Measure 10ID |
Erwin |
Access Zone B |
1000-1100 |
Map SR dipole bus structure |
Wang |
Access Zone B |
1000-1100 |
Map water leaks |
Pasky, FMS, S&A |
Access Booster |
1100-1200 |
Run ITS cables |
Pasky |
Access Linac |
1100-1200 |
Tune PID loops |
Erwin |
No Beam |
1130-1230 |
investigate network storm problems |
Lill, Shoaf, Leibfritz |
No Beam |
1230-1300 |
Recover systems -- store beam |
OPS |
Stored beam & injection |
|
|
|
|
1500-1900 |
Complete hybrid setup (including P0 setup with C. Yao) - before orbit switch. |
Sajaev/Yao |
Stored beam & injection |
1900-2300 |
Orbit switch |
Xiao |
Stored beam & injection |
2300-2400 |
Investigate bpm weirdness |
Sereno, Emery |
Stored beam & injection |
|
Tuesday, February 25, 2014 |
|
|
0000-0300 |
Investigate bpm weirdness (continued) |
Sereno, Emery |
Stored beam & injection |
0300-0500 |
Vertical scraper scan |
Emery |
Stored beam & injection |
0500-0700 |
Linac training (23-07) |
Frausto |
Limited Injection |
0700-0830 |
Storage-ring training |
Obosahon |
Stored beam & injection |
0830-0900 |
Switch Pump 517 (S20A - Sec. 19&20) to standby pump -- affected P.S. set to 0 |
Wright |
No beam |
0900-12:30 |
IEX tests |
Smith, M. |
No beam |
0800-1100 |
RG1 studies |
Pasky |
Limited injection |
1100-1300 |
setup and run booster I-Ramp correction with beam |
Yao, Shang |
Limited injection |
1300-1500 |
More hybrid set-up |
Sajaev |
Stored beam & injection |
1500-1900 |
Nonlinearity vs chromaticity tests for P0 feedback performance |
Sajaev |
Stored beam & injection |
1900-2400 |
mombo XBPM gap scan |
Sereno |
Stored beam & injection |
|
Wednesday, February 26, 2014 |
|
|
0000-0400 |
mombo XBPM gap scan (continued) |
Sereno |
Stored beam & injection |
0400-0600 |
Linac training (23-07) |
Frausto |
Limited Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |