Machine Studies

Draft Schedule for Run01-7, 2014

March 11th 0800 – March 12th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, March 11, 2014



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1030

RF waveguide switch from 1&2 to 3&4

RF Group

No Beam

0930-1030

test the upgrade of iocsbpmdp

S. Xu

No Beam

0930-1130

Investigate intermittent rf source amplitude and phase changes

RF Group

No Beam

0930-1130

spare RF cable routing in A014

Berenc

No impact

0930-1130

Testing PAR wavetek afg with new device support

DiMonte

No injection

0930-1130

scope the +5V in all the SR converter cabinets in Zone B

Puttkammer

No beam

0930-1130

Continue troubleshooting RF2 modulator card waveform

RF Group

No Beam

1000-1030

Switch from back-up pump SR20B to primary 20A (P.S. in S19&20 at 0)

Wright

No Beam

1000-1030

Measure 35ID I monitor bellows

Erwin/Izzo

Access Zone F

1030-1130

10ID chamber measurements

Erwin

Access Zone B

1130-1200

Recover stored beam

OPS


1200-1400

Setup new ramp configuration for test during study

Yao, Shang

Limited injection

1400-1800

Vertical kicker beam dump studies

Harkay, Dooling

Stored beam & injection

1800-2000

Linac training (15-23)

Frausto

Limited Injection

2000-2400

Orbit switch

Xiao

Stored beam & injection


Wednesday, March 12, 2014



0000-0400

Fine tune IEX tables

Xiao

Stored beam & injection

0400-0600

Booster training (23-07) (continued)

Angel

Limited Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection