Machine Studies

Schedule for Run02-1, 2014

May 22nd 0800 – May 28th 0800

Time

Descriptions

Studiers

SR Status


Thursday, May 22, 2014



0800-1200

BPLD validations

Bui

Stored beam & injection

1200-1300

Storage Ring training (07-15)

Angel

Stored beam & inj.

1300-1700

X-ray BPM checkout

Hahne

Stored beam & Occ. inj.

1700-2300

Initial BPM checkout

Sereno

Stored beam & injection

2300-2400

BPM offset measurement

Xiao

Stored beam & injection


Friday, May 23, 2014



0000-0300

BPM offset measurement (continued)

Xiao

Stored beam & injection

0000-0200

PAR training

Fausto

Limited injection

0300-0700

Orbit recovery

Xiao

Stored beam & injection

0700-0900

Storage Ring training

Angel

Stored beam & injection

0900-1500

Initial lattice setup

Sajaev

Stored beam & injection

1500-1700

Test new tune measurement configuration

Yao/Shang

Stored beam & injection

1700-2100

Test ramp correction program new configuration

Yao/Shang

No injection

2100-2400

BPM offset measurement

Xiao

Stored beam & inection


Saturday, May 24, 2014



0000-0400

BPM offset measurement (continued

Xiao

Stored beam & injection

0100-0300

Storage Ring training

Obasohan

Stored beam & injection

0300-0800

OPEN



0800-1200

Optimize booster chromaticity correction with high charge

Yao

No injection

1200-2200

CPU Checkout

Xiao

Stored beam & injection

2200-2400

OPEN




Sunday, May 25, 2014



0000-0200

Storage ring training

Obasohan

Stored beam & injection

1000-2000

IEX Checkout

Xiao

Stored beam & injection

2000-2400

OPEN




Monday, May 26, 2014



0000-0200

Storage ring training

Obasohan

Stored beam & injection

0200-1000

Top-up checkout

OPS

Stored beam & injection

1000-1200

Final pinhole camera setup & bunch purity setup

Yang

Stored beam & injection

1200-1600

Grid XBPM studies

Yang/Sereno

Stored beam & injection

1600-2400

OPEN




Tueday, May 27, 2014



0000-0600

Skew quad checkout

Sajaev

Stored beam & injection

0600-1200

Final BPM checkout

Sereno

Stored beam & injection

1200-1700

Shielding verification 35-ID

Ramanathan

Stored beam & injection

1700-1900

SCU0 skew quad feedforward checkout, 100 mA, 24 bunches

Harkay/Emery

Stored beam & injection

1900-2300

Final orbit checkout

Xiao

Stored beam & injection

2300-2400

Storage ring training

Obasohan

Stored beam & injection


Wednesday, May 28, 2014



0000-0100

Storage ring training

Obasohan

Stored beam & injection

0100-0630

Final lattice setup

Sajaev

Stored beam & injection

0630-0700

Switch from P-RF3 to backup pump (WR#33650) -- RF2 in diode mode

MOM group

No beam

0700-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection