Draft Schedule for Run02-9, 2014

July 22th 0800 – July  23rd 0800

 

Time

Descriptions

Studiers

SR Status

 

Tuesday, July 22, 2014

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Repair capacitor temp readbacks

Jordan

No Beam

0930-1130

Swap quad converters in Zone A

Vargas

No Beam

0930-1130

Measure fast corrector frequency spectrum

Wang

No Beam

0930-1130

IEX PS update

Deriy/Smith

No Beam

0930-1130

Linac BESOCM offset study

Sereno

Beam in Linac

1000-1200

Bring server Sol back on line

Thurman

No Beam – Intermittent network availability

1200-1600

Check P1 offset measurement data and install

Ops/Xiao

Stored Beam & Injection

1200-1400

SR training (09-15)

Angel

Stored Beam & Injection

1400-1600

Measure booster chromaticity

Yao

Limited Injection

1600-1800

Test upgrade of multiple SR BPM iocs

Xu

Stored Beam & Injection

1800-2200

Unified feedback studies

Sereno/Carwardine/Emery

Stored Beam & Injection

2200-2400

Mombo gap scans

Sereno/Shang

Stored Beam & Injection

 

Wednesday, July 23, 2014

 

 

0000-0200

Mombo gap scans

Sereno/Shang

Stored Beam & Injection

0200-0700

Measure beam motion noise

Sajaev

Stored Beam & Injection

0500-0700

Linac training

Henry

Limited Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection