Machine Studies
Draft Schedule for Run03-2, 2014
October 7th 0800 – October 8th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, October 7, 2014 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Switch from back up to pump 513/514 |
Wright |
Affected PS at zero |
0930-1000 |
Visually check wiring in S35 ASIE |
Forrestal |
Stored Beam & Injection |
0930-1030 |
Replace DAS DSP in iocs1fb |
Lenkszus |
No beam |
0930-1030 |
Install GridXbpm software S27 &35 |
Lenkszus |
No Beam |
1030-1330 |
Waveguide switch to RF-1 and make adjustments to RF1 |
RF Group |
No Beam |
0930-1030 |
Investigate the Booster Extraction interlock PLC |
DiMonte/RF Group |
No Injection |
0930-1130 |
Replace SAMMS unit on starter for process water pump 509 (P-509, P-510 off) |
Kailus |
Affected power supplies off |
0930-1130 |
Repair MCC bucket for AHU 5009 (P-517, P-518 off) |
Kailus |
Affected power supplies off |
0930-1130 |
Replace S14 interface board |
Vargas |
No Beam |
0930-1130 |
Repair ground fault in S26/27 R2 |
Jordan |
No Beam |
0930-1330 |
Verify PC gun connections and comm |
T. Smith |
Limited Injection |
1000-1030 |
Linac bucking coil polarity check |
Sun |
Access Linac |
1330-1530 |
Check out adjustments to RF-1 at 102mA (top-up needed) |
RF Group |
Stored beam & injection |
1530-1800 |
check P0 feedback and measure accumulation limit |
Yao |
Stored beam & injection |
1530-1800 |
Investigate on-going injection problem |
|
|
1800-2100 |
Mombo scans |
Sereno |
Stored beam & injection |
2100-2300 |
Booster training (15-23) |
Frausto |
Limited Injection |
2300-2400 |
correct beta functions in the linac |
Sun, Y./Dooling |
Limited Injection |
|
Wednesday, October 8, 2014 |
|
|
0000-0200 |
correct beta functions in the linac |
|
|
0200-0500 |
ID1 BLM studies |
Harkay/Dooling |
Stored beam & injection |
0500-0700 |
PAR training (23-07) |
Henry |
Limited Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |