November 4th 0800 – November 5th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, November 4, 2014 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving DSPs |
PS Group |
Limited Injection |
0930-1130 |
Swap out older Quad converters in S8/9 |
Vargas |
No Beam |
0930-1130 |
Investigate loss of communications at S40 Cab 1 PSCU |
Fors |
No beam |
0930-1130 |
Measure water flows in SR raws |
Goetzen |
No Beam |
0930-1130 |
Switch from pump 531 to 532. Repair 531 |
Wright |
No Beam |
1000-1100 |
Troubleshoot LTP:FL1 |
Wright |
Access PAR |
1000-1100 |
Tcavity mapping |
T. Smith |
Access Linac |
1130-1300 |
SR training (07-15) |
Angel |
Stored Beam & Injection |
1300-1500 |
test SR single bunch current limit vs amplifier power |
Yao |
Stored Beam & injection |
1500-1800 |
P0/GRID studies |
Sereno |
Stored Beam & injection |
1800-2100 |
unified feedback studies to test steering and calculation of DP response matrix from theory |
Sereno |
Stored beam & injection |
2100-2400 |
Investigate injection bump and beam separation |
Sajaev, Yipeng Sun |
Stored beam & injection |
|
Wednesday, November 5, 2014 |
|
|
000-0400 |
Switch orbit (continued) |
Sajaev |
Stored beam & injection |
0400-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |