Machine Studies

Draft Schedule for Run03-7, 2014

November 11th 0800 – November 12th 0800

Time

Descriptions

Studiers

SR Status


Tuesday, November 11, 2014



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/

OPS

Stored Beam & Injection

0930-1000

RF waveguide switch

RF Group

No Beam

0930-1200

Replace the 5kv bias cage and fiber optic "ready" cable within RF4's mod-anode tank (may need an extra hour)

RF Group

No Beam

0930-1000

Switch back to pump 531

Wright

No Beam

0930-1030

Pull cables on SR mezzanine

Diag Group

No Impact

0930-1130

Swap out quad supplies in S8/9

Vargas

No Beam

0930-1130

Measure Zone A water flows

Goetzen

No Beam

0930-1130

AHU work S27/28 & S37/38

FMS

No Impact

1000-1200

Measure booster chromaticity

Yao

No Beam

1000-1130

Install IR camera at 27ID

Erwin

Access Zone D

1130-1200

Recover storage ring

OPS

No beam

1200-1300

SR training (09-15) (may be displaced by RF Group work on 5kV bias cage if needed -- 0930-1200)

Angel

Stored Beam & Injection

1300-1500

Set up RHB lattice

Sajaev

Stored beam & injection

1500-1900

Orbit Switch

Xiao

Stored Beam & inection

1900-2100

S27 Libera P0's in feedback studies

Sereno

Stored beam & injection

2100-2300

S27, S35 GRID XBPM scans/studies

Sereno

Stored beam & injection

2300-2400

unified feedback studies

Sereno

Stored beam & injection


Wednesday, November 12, 2014



0000-0100

unified feedback studies (continued)

Sereno

Stored beam & injection

0100-0230

Injector training (23-07)

Henry

Limited Injection

0230-0630

local impedance bump

Emery

Stored Beam & injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection