Machine Studies
Draft Schedule for Run01-5, 2015
March 2nd 0800 – March 4th 0800
Time | Descriptions | Studiers | SR Status |
| Monday, March 2, 2015 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0930 | Gap Scans and update IDGapFF look-up tables | Schroeder | Stored Beam & Injection |
0930-1000 | Reboot interleaving DSPs | PS group | No Injection |
0930-1000 | RF waveguide switch from RF2 to RF3 | RF Group | No Beam |
0930-1130 | Feedback IOC work | Lenkszus | No Beam |
0930-1130 | Swap converters for IGBT upgrade S8 | Vargas | No Beam |
0930-1130 | Replace water hoses in Zone D raws. | Goetzen | No Beam |
1000-1100 | Repair PTB:FL1 | MOM | Access Linac |
1000-1200 | Replace PFN load cable for RG2 | Donkers/Vanis | Access Linac |
1000-1400 | Swap out RF Gun1 | Hoyt, MOM | Access Linac |
1015-1215 | Replace temp sensors at S33B:QS | Wright | Access Zone E |
1130-1400 | Test startDigitizer timing change | Lenkszus/Yao Shang/Laird | No Beam |
1400-1700 | Take measurements of PAR RF-12 #1 | RF Group | Stored Beam & Injection |
1430-1700 | L2 & 3 RF power measurements | RF Group | Limited Injection |
1500-1700 | Setup S1A BPMs for turn-by-turn measurement | Sajaev | Limited Injection |
1700-2100 | Hybrid setup with P0 feedback and CPU | Sajaev/Yao /Xiao | Stored Beam & Injection |
2100-2300 | Linac training (15-23) | E. Smith | Limited Injection |
2300-2400 | Booster training (23-07) | Henry | Limited Injection |
| Tuesday, March 3, 2015 |
|
|
0000-0100 | Booster training (23-07) | Henry | Limited Injection |
0100-0500 | Orbit Switch | Xiao | Stored Beam & Injection |
0500-0800 | Hybrid with CPU on | Xiao | Stored Beam & Injection |
0800-1000 | Remove bakeout equipment from RG-1 | Hoyt | Access Linac |
0800-1000 | Test startDigitizer timing change | Lenkszus/Yao Shang/Laird | No Beam |
1000-1300 | RG2 Tuning | Yin-e Sun /Dooling | Limited Injection |
1000-1300 | Test 4x4 RTFB at S27 | Lenkszus /Sereno/Xu | Limited Injection |
1300-1500 | Par beam size measurement | Yao/Harkay /Calvey | Par beam only |
1500-1800 | Booster rf frequency scan | Yao | Booster beam only |
1800-2000 | Linac training (15-23) | E. Smith | Limited Injection |
1800-2100 | ID4 physical aperture | Yi-peng Sun/Emery | Limited Injection |
2100-2400 | RG1 condition | Pasky/Dooling | No Beam |
| Wednesday, March 4, 2015 |
|
|
0000-0130 | RG1 condition | Pasky/Dooling | No Beam |
0130-0330 | Booster training (23-07) | Henry | Limited Injection |
0330-0630 | ID4 Local impedance measurement | Sajaev | Stored Beam & Injection |
0630-0800 | Prepare for User beam | OPS | Stored Beam & Injection |