Machine Studies

Draft Schedule for Run01-5, 2015

March 2nd 0800 – March 4th  0800

 

Time

Descriptions

Studiers

SR Status

 

Monday, March 2, 2015

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1000

Reboot interleaving DSPs

PS group

No Injection

0930-1000

RF waveguide switch from RF2 to RF3

RF Group

No Beam

0930-1130

Feedback IOC work

Lenkszus

No Beam

0930-1130

Swap converters for IGBT upgrade S8

Vargas

No Beam

0930-1130

Replace water hoses in Zone D raws.

Goetzen

No Beam

1000-1100

Repair PTB:FL1

MOM

Access Linac

1000-1200

Replace PFN load cable for RG2

Donkers/Vanis

Access Linac

1000-1400

Swap out RF Gun1

Hoyt, MOM

Access Linac

1015-1215

Replace temp sensors at S33B:QS

Wright

Access Zone E

1130-1400

Test startDigitizer timing change

Lenkszus/Yao

Shang/Laird

No Beam

1400-1700

Take measurements of PAR RF-12 #1

RF Group

Stored Beam & Injection

1430-1700

L2 & 3 RF power measurements

RF Group

Limited Injection

1500-1700

Setup S1A BPMs for turn-by-turn measurement

Sajaev

Limited Injection

1700-2100

Hybrid setup with P0 feedback and CPU

Sajaev/Yao /Xiao

Stored Beam & Injection

2100-2300

Linac training (15-23)

E. Smith

Limited Injection

2300-2400

Booster training (23-07)

Henry

Limited Injection

 

Tuesday, March 3, 2015

 

 

0000-0100

Booster training (23-07)

Henry

Limited Injection

0100-0500

Orbit Switch

Xiao

Stored Beam & Injection

0500-0800

Hybrid with CPU on

Xiao

Stored Beam & Injection

0800-1000

Remove bakeout equipment from RG-1

Hoyt

Access Linac

0800-1000

Test startDigitizer timing change

Lenkszus/Yao

Shang/Laird

No Beam

1000-1300

RG2 Tuning

Yin-e Sun

/Dooling

Limited Injection

1000-1300

Test 4x4 RTFB at S27

Lenkszus

/Sereno/Xu

Limited Injection

1300-1500

Par beam size measurement

Yao/Harkay

/Calvey

Par beam only

1500-1800

Booster rf frequency scan

Yao

Booster beam only

1800-2000

Linac training (15-23)

E. Smith

Limited Injection

1800-2100

ID4 physical aperture

Yi-peng Sun/Emery

Limited Injection

2100-2400

RG1 condition

Pasky/Dooling

No Beam

 

Wednesday, March 4, 2015

 

 

0000-0130

RG1 condition

Pasky/Dooling

No Beam

0130-0330

Booster training (23-07)

Henry

Limited Injection

0330-0630

ID4 Local impedance measurement

Sajaev

Stored Beam & Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection