Machine Studies

Draft Schedule for Run01-9, 2015

March 31st 0800 – April 1st 0800

 

Time

Descriptions

Studiers

SR Status

 

Tuesday, March 31, 2015

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Swap SR Quads in S7

Ackley

No Beam

0930-1130

Test DSP in iocs3fb

Lenkszus

No Beam

0930-1130

Update calibration for BTS I monitor

Pietryla

Limited Injection

0930-1130

 

Work on BPM rack temperature regulation

Erwin

No Beam

0930-1130

Linac L1/L3 VDM Interchangeability test.

Ma

No Injection

1130-1200

Recover SR

OPS

Stored Beam & Injection

1200-1700

S27 GRID/Libera P0 calibration

Sereno

Stored Beam & Injection

1700-1900

Orbit stability investment

Sereno/Emery

Stored Beam & Injection

1900-2000

Beam Loss Study with FPGA

Harkay/Dooling

Stored Beam & Injection

2000-2400

PAR tune measurement

Calvey/Yao/Harkay

Limited Injection

2000-2200

SR training (15-23)

Henry

Limited Injection

2200-2400

MPS backup signal test

Yao/Xiao

Limited Injection

 

Wednesday, April 1, 2015

 

 

0000-0400

Injection efficiency for Hybrid

Sun-yipeng/Emery

Stored Beam & Injection

0400-0630

Return optics to RHB

OPS

Limited Injection

0400-0700

RG1 tune up

Pasky/Dooling

Limited Injection

0630-0700

Reinstall original DSP in iocs3fb

Lenkszus

No Beam

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection