Draft Schedule for Run02-1, 2015
May 26th 0800 – May 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, May 26, 2015 |
|
|
0800-1300 |
Create Linac files/ activate RG-2 |
Pasky, Sun |
Stored Beam & Injection |
0800-1000 |
Install and test “Valid” PV’s for GridXbpms |
Lenkszus |
No Beam |
0830-0930 |
Flip ID4 canted PM |
Grimmer |
Access Zone A |
0800-1200 |
Fix valve in S26 |
Wright |
S25-28 PS off |
0800-1000 |
Test booster injection in DC-standby mode |
Yao/Puttkammer |
No beam |
1000-1030 |
Replace module in iocmtime |
Lenkszus |
No Beam |
1330-1530 |
Reinstall optics |
Dooling |
Access Linac (may be bumped if RFG work dictates) |
1600-2000 |
Turn-by-turn BPM scripts and test for inclusion of S1 BPMs |
Sajaev |
Stored beam & injection |
2000-2200 |
SR training (15-23) |
Frausto |
Limited Injection |
2200-2400 |
OPEN |
|
|
|
Wednesday, May 27, 2015 |
|
|
0000-0700 |
OPEN |
|
|
0700-1200 |
BPLD validationss |
Erwin |
Stored Beam & Injection |
1200-1500 |
X-ray bpm checkout |
Erwin |
Stored Beam & Injection |
1500-1700 |
ID4 aperture |
Emery |
Stored Beam & Injection |
1700-1900 |
ID1 aperture (more detailed than the SCU1 commissioning) |
Emery |
Stored Beam & Injection |
1900-2300 |
Install non-symmetric sextupoles from Jan for regular 24 singlet running. |
Emery |
Stored Beam & Injection |
2300-2400 |
optics correction, coupling correction on the above |
Sajaev |
Stored Beam & Injection |
|
Thursday, May 28, 2015 |
|
|
0000-0300 |
optics correction, coupling correction on the above |
Sajaev |
Stored Beam & Injection |
0300-0700 |
Orbit recovery |
Xiao |
Stored Beam & Injection |
0700-0900 |
BPM offset measurement |
Xiao |
Stored Beam & Injection |
0900-1000 |
Check out hardware and triggering abort kicker |
Wang, Lenkzsus |
No beam |
1000-1200 |
MPS + kicker beam dumps with HP radiation measurements in S39, etc. |
Harkay, Dooling, Vacca |
Stored beam & injection |
1200-1330 |
MPS rf bypass + kicker beam dumps |
Harkay, Dooling, Horan |
Stored beam & injection |
1330-1400 |
restore MPS and do MPS validation. |
Horan/OPS |
No beam |
1400-1800 |
PAR ion effect investigation. PAR and Booster beam |
Yao, Calvey, Harkay |
Occasional injection |
1400-1800 |
Test SCU0 without beam |
MD Group |
No beam |
1400-1800 |
Test SCU1 without beam |
1-ID beamline |
No beam |
1800-2200 |
Check efficiency versus tune |
Emery |
Stored beam & injection |
2200-2400 |
ID4 impedance by local bump |
Emery |
Stored beam & injection |
|
Friday, May 29, 2015 |
|
|
0000-0200 |
ID4 impedance by local bump |
Emery |
Stored beam & injection |
0200-0800 |
CPU checkout I |
Xiao |
|
0800-1300 |
Intermediate lattice correction |
Sajaev |
Stored beam & injection |
1300-1700 |
Commission BSP100 BPs and measure response |
Yao, Shang, Pietryla, Bui |
Limited injection |
1700-2100 |
measure booster charge dependent tune shift of 132 nm lattice. Booster beam. |
Yao |
Stored beam |
2100-2400 |
DC-mode booster beam test. Booster injection only |
Yao |
Stored beam |
|
Saturday, May 30, 2015 |
|
|
0000-0200 |
Storage ring training (Frausto) |
Frausto |
Stored beam & injection |
0200-0800 |
Test of Compton X-ray BPMs at 24-ID (shutter open) |
Yang |
Stored beam & injection |
0800-1200 |
more detailed injection efficiency |
Emery |
Stored beam & injection |
1200-1800 |
CPU checkout II |
Xiao |
Stored beam |
1800-2200 |
X-ray BPM checkout |
Erwin |
Stored beam & injection |
2200-2400 |
Top-up Verification |
OPS |
Stored beam & injection |
|
Sunday, May 31, 2015 |
|
|
0000-0800 |
Top-up Verification |
OPS |
Stored beam & injection |
0800-1000 |
Storage ring training (2300-1100) |
Frausto |
Stored beam & injection |
1000-1800 |
IEX checkout |
Xiao |
Stored beam |
1800-2400 |
BPM offset measurements (or Top-up Verification if needed) |
OPS |
Stored beam & injection |
|
Monday, June 1, 2015 |
|
|
0000-0500 |
BPM offset measurements (or Top-up Verification if needed) |
OPS |
Stored beam & injection |
0500-0700 |
Storage-ring training |
Frausto |
Stored beam & injection |
0700-1000 |
PAR radiation survey with 1 nC charge. PAR beam |
Yao, Vacca |
No injection |
0800-1000 |
Continuation of IOCs36cav hang-up issues |
Di Monte |
No beam |
1000-1800 |
ID-1 & SCU1 checkout with 1-ID beamline (shutter permit needed) |
Emery, OPS, 1-ID |
Stored beam & injection |
1800-2000 |
SCU0 feedforward check-out |
Harkay |
Stored beam & injection |
2000-2200 |
Final S35-BM pinhole camera set-up |
Yang |
Stored beam & injection |
2200-2400 |
Bunch purity set-up |
Yang |
Stored beam & injection |
|
Tuesday, June 2, 2015 |
|
|
0000-0500 |
Final lattice set-up |
Sajaev |
Stored beam & injection |
0630-0800 |
Prepare for User operations |
OPS |
Stored beam & injection |