Machine Studies
Draft Schedule for Run02-4, 2015
June 23th 0800 - June 24th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, June 23, 2015 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Test GridXbpm software iocs27fb |
Lenkszus |
No Beam |
0930-1030 |
Switch driver amplifier for PAR RF1 |
RF Group |
No Injection |
0930-1030 |
Test RF1 modified device support |
DiMonte |
No Beam |
0930-1130 |
Swap out quad converters in S32/33 |
Ackley |
No Beam |
0930-1130 |
Investigate BEK OV trips |
Donkers |
No Injection |
0930-1130 |
Add DAC filter to SR converters in 32B:Q5 & 20A:Q3 |
Jordan |
No Beam |
1000-1030 |
Check for water leakage |
Pasky |
Access Booster |
1030-1130 |
Verify operation of PAR RF1 drive amp |
RF Group |
Limited Injection |
1130-1200 |
Restore driver amplifier for PAR RF1 |
RF Group |
Limited injection |
1200-1400 |
Test Booster BSP-100 |
Yao, Shang |
Limited injection |
1400-1600 |
Set-up Hybrid RHB lattice |
Sajaev |
Stored beam & injection |
1600-1730 |
Orbits on resonance |
Sun, Yipeng |
Stored beam & injection |
1730-1830 |
Radiation survey of abort kicker tests |
Harkay, Dooling, Vacca |
Storeed beam & injection |
1830-2200 |
Test of Comptom Xbpms in S24 (shutter permit needed) -- Parallel to S27 GRID XBPM study |
Yang |
Stored beam & injection |
1900-2200 |
S27 GRID XBPM in Datapool feedback studies -- Parallel to S24 Compton Xbpm study |
Sereno/Yang |
Stored beam & injection |
2200-2400 |
Mombo scans |
Sereno |
Stored beam & injection |
|
Wednesday, June 24, 2015 |
|
|
0000-0200 |
Mombo Scans (continued) |
Sereno |
Stored beam & injection |
0200-0600 |
Set up orbit for Hybrid RHB |
Xiao |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |