Draft Schedule for Run03-12, 2015
December 21st 0800 – December 21st 2400
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 21, 2015 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam |
0810-1200 |
booster bump scan study |
Yao |
Stored Beam |
1000-1200 |
Replace VME processors in insertion device IOCs in sectors 2 - 12 |
M. Smith |
Stored Beam |
1200-1330 |
ID1/SCU1 beam-based alignment. 25 mA in 24 bunches |
Harkay |
Stored Beam & Inj. |
1330-1730 |
S27,35,24 GRID/Compton Xbpm studies (35-ID shutter may need to be opened) |
Yang/Sereno |
Stored Beam & injection |
1730-1830 |
test 4x4 feedback matrix in vertical plane in sector 27 |
Sereno |
Stored Beam & Inj. |
1830-2200 |
test unified feedback with Louis' new steering procedure |
Sereno |
Stored Beam & Inj. |
2200-2400 |
"Gentle" shutdown of SR |
OPS |