Machine Studies
Draft Schedule for Run03-2, 2015
October 13th 0800 – October 14th 0800
Time | Descriptions | Studiers | SR Status |
| Tuesday, October 13, 2015 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-1000 | Gap Scans and update IDGapFF look-up tables | Schroeder | Stored Beam & Injection |
1000-1100 | Re-enable ASYNC timing for L6 | Pietryla | No Injection |
1000-1100 | IOCS27BPM PV testing | Lenkszus | No Beam |
1000-1100 | 14ID end to end test | Budz | No Beam |
1000-1200 | Replace S36 Cav. 4 blower |
| Access Zone F |
1000-1200 | CPU database testing | Smith | No Beam |
1000-1200 | Investigate L2:QM7 read back issues | Donkers | Limited Injection |
1000-1200 | Inspect B:ES2 PS cabinet | Goetzen | No Injection |
1000-1200 | Measure interlock cable on S4B:V3 | Vargas | No Beam |
1100-1200 | Check 1 Hz timing and BM ramp | Yao/Lenkszus/Wang | No Beam |
1200-1400 | Measure DC ramp lattice | Yao | No Injection |
1400-1500 | Operator re-qualification | Fystro/Schroeder | Stored beam & Injection |
1500-1600 | Test changes to single gap scan PEM | Shang/Schroeder | Stored beam & Injection |
1600-1700 | Operator re-qualification | Bogdan/Schroeder | Stored beam & Injection |
1700-1900 | Investigate S32 XBPM | Hahne | Stored beam & Injection |
1900-2200 | Compton XBPM study | Yang/Sereno | Stored beam & Injection |
2200-2400 | Calibrate Libera B+ bpms | Sereno | Stored beam & Injection |
| Wednesday, October 14, 2015 |
|
|
0000-0100 | Calibrate Libera B+ bpms | Sereno | Stored beam & Injection |
0100-0500 | PAR Ion study | Calvey/Yao/Harkay | No Injection |
0500-0700 | 48-bunch instability | Harkay | Stored beam & Injection |
0700-0800 | Prepare for User beam | OPS | Stored Beam & Injection |