November 10th 0800 – November 11th 0800

 

Time

Descriptions

Studiers

SR Status

 

Tuesday, November 10, 2015

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1000

34ID end to end test

McNamara

No Beam

0930-1130

Swap sextupoles in S1 & 35

Vargas

No Beam

0930-1130

Swap out S13 & 14 quads

Ackley

No  Beam

0930-1130

Check BES2 protection diode

Vanis

Limited Injection

0930-1130

Investigate trigger cabling for libpm iocs

Pietryla

No Injection

0930-1130

SR AHU work

Erwin/FMS

No Beam /IEX off

0930-1130

Start and test PV gateways for FPGA bpm

Smith

No Beam

0930-1130

Test/Install local steering enhanced DP

Lenkszus

No Beam

0930-1230

Troubleshoot RF5 OI trips

RF Group

No Injection

1000-1030

Measure cable run from L6 to ITS

Goel

Access Linac

1100-1200

Investigate L2:QM7

Donkers

No Injection

1230-1330

Test Gap Scan Changes

Schroeder/Shang

Stored Beam & Injection

1330-1730

1 Hz Booster Study

Yao/Shang

Limited Injection

1330-1730

Libera P0 feedback study

Sereno

Limited Injection

1730-1830

SR operator re-qualification

Ronzhin/Schroeder

Stored Beam & Injection

1830-2200

MOMBO Gap Scan

Hahne

Stored Beam & Injection

2200-2400

New S32 RHB test

Sajaev/SunYP

Stored Beam & Injection

 

Wednesday, November 11, 2015

 

 

0000-0200

New S32 RHB test

Sajaev/SunYP

Stored Beam & Injection

0200-0500

Bump steering test

Emery/Shang

Stored Beam & Injection

0500-0700

Calibration of fast BLM in ID6

Dooling/Harkay

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection