Machine Studies

Draft Schedule for Run03-9, 2015

December 1st 0800 – December 2nd 0800

 

Time

Descriptions

Studiers

SR Status

 

Tuesday, December 1, 2015

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1000

RF waveguide switch

RF Group

No Beam

0930-1130

Troubleshoot RF-4 cathod votage stability

RF Group

No Beam

0930-1130

Swap out SR quads in S15/16

Ackley/Jordan

No Beam

0930-1130

Investigate B:SD output fuse issue

Puttkammer

No Injection

0930-1130

Bring new air compressor on line

Kailus

No Beam

1000-1015

L2:AS1 measurements

Bromberek

Access Linac

1015-1200

PC gun laser alignment

Dooling

Access Linac

1200-1230

Recover injectors

OPS

Stored Beam & Injection

1230-1330

Check S2 P0 amplifier

Yao

Stored Beam & Injection

1330-1730

ID24 thermal imaging + ID27/35 Grid XBPM study

Sereno

Stored Beam & Injection

1730-2130

 Libera P0, S27 GRID and Mechanical Motion Sensing System integrated studies

Sereno

Stored Beam & Injection

2130-2330

Abort Kicker study

Harkay/Dooling/Sajaev

Stored Beam & Injection

2330-2400

Booster DC ramp

Yao

Booster beam only

 

Wednesday, December 2, 2015

 

 

0000-0330

Booster DC ramp

Yao

Booster beam only

0330-0630

Non symmetric-bump impedance measurement

Emery

Stored Beam & Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection