Draft Schedule for Run01-2, 2016
February 9th 0800 - February 10th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, Feburary 09, 2015 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1130 |
Swap out quad converters in S36/38 |
Ackley/Jordan |
No Beam |
0930-1130 |
Replace CBR relay in S6:7 T4 raw |
Vargas |
No Beam |
0930-1130 |
Replace +24V supply in L2 rack |
Donkers |
No Injection |
0930-1130 |
Upgrade SR AK0 strobe |
Vanis |
No Beam |
0930-1130 |
Investigate S8:9 communication loss |
Jordan |
No Beam |
0930-1230 |
Investigate RF4 cathode regulation problem |
RF Group |
No Beam |
0930-1230 |
Booster long ramp tuning |
Yao |
No Injection |
0930-1230 |
Connect and validate L1/6 interlocks |
Pietryla/Pasky |
No Injection |
1000-1200 |
Troubleshoot PC gun YAG lens control |
Berg |
Access Linac |
1000-1015 |
Measure residual field of gun spectrometer |
Sun |
Access Linac |
1000-1300 |
Survey measurements around Tcav |
Smith, T. |
Access Linac |
1000-1100 |
Replace the two monopulse receivers in S27B:P2 and S27B:P3 |
Blake |
No beam |
1230-1430 |
Energize and test RF-1 matching transformer |
RF Group |
Stored Beam & Injection |
1300-1330 |
Recover Injectors & SR |
OPS |
Stored Beam & injection |
1330-1530 |
Continue RG1 set-up |
Yin-E Sun, Dooling, Pasky |
Limited injection |
1330-1530 |
Investigate S27B:P2 in feedback (see if we can put it back after doing orbit transfer and gap scan) |
Sereno |
Stored Beam & Occ. inj. |
1530-1700 |
Complete PAR radiation survey |
Yao, Vacca |
No injection |
1700-1800 |
measure P0 feedback noise, require 24 single stored beam and change chromaticity |
Yao |
Stored beam & injection |
1800-2200 |
test of helical SCU lattice |
Sajaev |
Stored beam & injection |
2200-2400 |
injection/dynamic aperture measurements |
Sajaev |
Stored beam & injection |
|
Wednesday, February 10, 2015 |
|
|
0000-0100 |
injection/dynamic aperture measurements (continued) |
Sajaev |
Stored beam & injection |
0100-0700 |
SR injection study |
Xiao |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |