Machine Studies
Draft Schedule for Run01-4, 2016
February 23rd 0800 - February 24th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 23, 2016 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Update Televac controller/ reboot siocl1vac |
Benes |
No Injection |
0930-1130 |
Booster long ramp testing |
Yao |
No Injection |
0930-1130 |
Check out ID7 controls |
Smith, M. |
No Beam |
0930-1130 |
Investigate Cap/OT trip in S25A:S4 |
Vargas |
No Beam |
0930-1130 |
fix the comm issue in sector 30:31 |
Puttkammer |
No Beam |
0930-1130 |
Swap converters for IGBT upgrade S24/25 |
Ackley/Jordan |
No Beam |
0930-1330 |
Install focusing magnets in L3 |
RF Group |
Stored Beam & Injection |
0930-1130 |
Measure and adjust the FOCUS current values for L2 klystron |
RF Group |
No injection |
1000-1100 |
Re-align T-cav waveguide |
Smith, T. |
Access Linac |
1130-1200 |
Recover SR |
OPS |
|
1200-1300 |
Practice setting up four coupling values for the Feb 29th 8am-10am general user study and steering at 1BM |
Emery |
Stored Beam & injection |
1300-1700 |
Sector 27 4x4 feedback studies |
Sereno, et al |
Stored Beam & occ. injection |
1300-1400 |
BTX line new screen test |
Yao |
Injection possible |
1400-1700 |
Booster new BPM tes |
Yao, Pietryla, Shang |
Injection possible |
1700-2100 |
Injection study |
Xiao |
Stored beam & injection |
2100-2400 |
Set-up RG1 |
Yine Sun, Dooling |
Limited injection |
|
Wednesday, February 24, 2016 |
|
|
0000-0100 |
Set-up RG1 |
Yine Sun, Dooling |
Limited injection |
0100-0400 |
PC Gun Studies |
Yine Sun, Dooling |
No injection |
0400-0700 |
Polarization measurement (instructions to come from Emery) |
OPS |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |