Machine Studies

Draft Schedule for Run01-9, 2016

March 29th 0800 – March 30th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, March 29, 2016



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Swap SR quad converters S22/23

Ackley/Vargas

No Beam

0930-1200

Booster long ramp test

Yao

No Injection

0930-1230

Install new focus supplies in L3

RF Group

Limited Injection

1000-1200

Replace S38 cav 1 IR thermometer

Wright

Access Zone F

1030-1100

Replace encoder at S3

Merritt

Access Zone A

1300-1600

Add CU and BM steering to server

Emery, M Smith

Stored beam

1300-1600

troubleshoot booster BSP100 BPMs

Yao, Pietryla, Bui

Occasion injection poss.

1600-1900

Mombo Scans (part B)

Hahne

Stored beam & injection

1600-1800

New bunch current monitor process (324 singlets)

Emery, Sajaev

Stored beam

1900-2300

S27 4X4 feedback studies

Sereno, et al

Stored beam & occ. inj.

2300-2400

Orbit switch

Xiao

Stored beam & injection


Wednesday, March 30, 2016



0000-0300

Orbit switch

Xiao

Stored beam & injection

0300-0630

Injection study

Xiao, Emery

Stored beam & injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection