Draft Schedule for Run02-10, 2016

August 1st 0800 – August 2nd 0800



Time

Descriptions

Studiers

SR Status


Monday, August 1, 2016



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1030

Wavelength switch from RF3/4 to RF2/4

RF Group

No Beam

0930-1030

Check cavity photohelic gauge pressure

RF Group

No Injection

0930-1030

Repair water leak in RF-5 garage

RF Group

No Injection

0930-1130

Swap out sextupole PS for upgrade

Ackley

No Beam

1000-1100

Investigate limit switch at 12ID

Merritt

Access Zone B

1100-1110

Brief tour

Gluskin

Access Zone B

1130-1200

Recover SR

OPS

Stored Beam & Injection

1200-1400

Vertical acceptance measurement

Borland

Stored Beam & Injection

1400-1900

Mombo scans and software testing

Hahne/Shang

Stored Beam & Injection

1900-2300

6ID GRID study

Yang

Stored Beam & Injection

2300-2400

S27 feedback study

Sereno

Stored Beam & Injection


Wednesday, August 2, 2016



0000-0100

S27 feedback study

Sereno

Stored Beam & Injection

0100-0630

High charge booster study

Harkay/Yao/

Calvey, Berenc

Limited Injection

0100-0630

Setup HB Inj. lattice

Xiao

Limited Injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection