Machine Studies
Draft Schedule for Run02-3, 2016
June 13th 0800 - June 14th 0800
Time | Descriptions | Studiers | SR Status |
| Monday, June 13, 2016 |
|
|
0800-0810 | Collect XBPM orbit data | OPS | Stored Beam & Injection |
0810-0930 | Gap Scans and update IDGapFF look-up tables | Schroeder | Stored Beam & Injection |
0930-1130 | Test RF-5 LLRF modulator card | RF Group | No Injection |
0930-1130 | Troubleshoot Booster ramp waveforms | Yao, Fors | No Injection |
0930-1130 | Swap quads for upgrades | Vargas | No Beam |
1000-1200 | Relocate supplemental shielding | Theres | Access PAR |
1000-1200 | PAR RF-1 HOM measurements | RF Group | Access PAR |
1000-1200 | LTP:FS3 measurements | Erwin, Berg | Access PAR |
1000-1200 | Measure cable calibrations for L2 | RF Group | Access Linac |
1200-1230 | Recover Injectors | OPS | Stored Beam & Injection |
1230-1330 | Test run L2 | RF Group | Limited Injection |
1330-1500 | PAR radiation survey | Yao/Vacca | PAR beam only |
1500-1700 | Work on Linac Optics | Borland | No Injection |
1700-2100 | 1 Hz booster 132nm high charge study | Yao | Booster beam only |
2100-2400 | Dynamic aperture measurement | Y.P. Sun | Stored Beam & Injection |
| Tuesday, June 14, 2016 |
|
|
0000-0400 | ID4 local impedance measurement | Sajaev | Stored Beam & Injection |
0400-0700 | Open |
|
|
0700-0800 | Prepare for User beam | OPS | Stored Beam & Injection |