Machine Studies

Draft Schedule for Run02-8, 2016

July 18th 0800 - July 19th 0800

 

Time

Descriptions

Studiers

SR Status

 

Monday, July 18, 2016

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0815-1230

Install new Klystron at RF1 (Waveguide opened - RF1-5 off)

RF Group

No Beam

0830-0930

Check limit switch at 12IDus

Merritt

Access Zone B

0900-1100

Reconnect FO loss monitor cables and add lead shielding around the PMT detector box at 1-ID

Dooling, Blake

Access Zone A

0900-0930

Swap out the Bergoz card for 13A:P0

Erwin

No beam

0815-1100

Swap out SR quad converters

Ackley

No beam

1230-1300

Recover SR ring

OPS

Stored Beam & injection

1300-1500

Measure vertical acceptance

Borland

Stored Beam & injection

1500-1900

6ID GRID IOC software testing

Yang/Xu

Stored Beam & injection

1900-2300

S27 unified feedback study+Libera B+ IIR filter test

Sereno

Stored Beam & injection

2300-2400

Benchmark MOGA simulation

Y.P. Sun

Stored Beam & injection

 

Tuesday, July 19, 2016

 

 

0000-0100

Benchmark MOGA simulation

Y.P. Sun

Stored Beam & injection

0100-0700

324/432 bunch pattern

Emery/Xiao

Stored Beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection