Machine Pre-Studies
Schedule for Run03-1, 2016 (includes Pre-studies)
Sep 23rd 0800 – Oct. 4th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Fri, Sep 23, 2016 (Pre-Studies) |
|
|
0800-1000 |
MPS validations, final checkout |
Smith |
|
1200-1400 |
Establish injection. |
Schroeder, Sajaev |
Stored Beam & Injection |
1400-1600 |
Aperture scan, ID6 SCU(18-2) chamber, 15 mA in many bunches. |
Emery, Sajaev |
Stored Beam & Injection |
1600-2000 |
Beam-based alignment, ID6 and ID1 scan, 24 bunches < 25 mA. |
Harkay |
Stored Beam & Injection |
1700-1900 |
|
Jansma et al. |
Access Zone A |
2000-2300 |
Beam-based alignment, BM6 scan, 324 bunches < 25 mA. |
Harkay |
Stored Beam & Injection |
2300-2400 |
Rf conditioning, 115 mA, 24 bunches. Measure x,y tunes at intervals of 5 mA. No P0 FB. |
OPS |
Stored Beam & Injection |
|
Sat, Sep 24, 2016 (Pre-studies) |
|
|
0000-1500 |
Rf conditioning, 115 mA, 24 bunches. Measure x,y tunes at intervals of 5 mA. No P0 FB. NOT COMPLETED |
OPS |
Stored Beam & Injection |
|
STUDIES DELAYED |
|
|
|
Sun, Sep 25, 2016 (Pre-studies) |
|
|
|
STUDIES DELAYED |
|
|
|
Mon, Sep 26, 2016 (Pre-studies) |
|
|
|
STORAGE RING STUDIES DELAYED |
|
|
0800-1500 |
Set up match on RG2 and files for RG1 |
Pasky, Yine Sun |
Limited injection |
1300-1400 |
Access Booster to check attenuator for BTX MBA kicker |
Yao, Keane |
No Booster beam |
1500-1700 |
Check-out BTX MBA kicker (no steering) |
|
|
1500-2400 |
Troubleshooting elevated vacuum at L5 |
|
|
|
Tuesday, Sep 27, 2016 (Pre-studies end at 08:00) |
|
|
0000-2400 |
All Studies Delayed. Troubleshooting/replacing window/conditioning at L5 |
|
|
|
Wednesday, Sep 28, 2016 |
|
|
0000-2400 |
All Studies Delayed. Troubleshooting/replacing window/conditioning at L5 |
|
|
|
Thursday, Sep 29, 2016 |
|
|
0000-1000 |
All Studies Delayed. Troubleshooting/replacing window/conditioning at L5 |
|
|
1000-1600 |
Get beam through injectors |
|
|
1600-2400 |
Rf conditioning, 115 mA, 24 bunches. Measure x,y tunes at intervals of 5 mA. No P0 FB. |
OPS |
Stored beam & injection |
|
Friday, Sep 30, 2016 |
|
|
0000-0500 |
Rf conditioning, 115 mA, 24 bunches. Measure x,y tunes at intervals of 5 mA. No P0 FB. |
OPS |
Stored beam & injection |
0500-0700 |
Accumulate 100 mA, 24 bunches, ID6 SCU powered |
Sajaev |
Stored beam & injection |
0700-1100 |
BPLD Validations |
Erwin |
Stored Beam & Injection |
1100-1400 |
X-ray BPM sanity check |
Hahne |
Stored Beam & Injection |
1100-1400 |
Initial Pinhole camera setup |
Yang |
Stored Beam & Injection |
1400-1600 |
Set-up P0 feedback |
Yao |
Stored Beam & injection |
1600-1800 |
BPM offset measurements |
Xiao |
Stored Beam & injection |
1800-2200 |
Orbit recovery |
Xiao |
Stored Beam & injection |
2200-2400 |
S27 Grid X-ray BPMs commissioning |
Sereno, Yang |
Stored beam & injection |
|
Saturday, Oct. 1, 2016 |
|
|
0000-0200 |
S27 Grid X-ray BPMs commissioning |
Sereno, Yang |
Stored beam & injection |
0200-0600 |
Beam perturbation and field integrals test for ID6 SCU, check out skew quad FF |
Emery/Sajaev |
Stored Beam & Injection |
0600-1000 |
Quench test, ID6 SCU powered |
Emery |
Stored Beam & Injection |
1000-1600 |
CPU checkout I |
Xiao |
Occ injection. |
1000-1600 |
Possible Booster study TBA (not high charge) |
Calvey |
Occ. injection possible |
1600-2000 |
S27 XBPM commissioning |
Sereno, Yang |
Stored beam & injection |
2000-2400 |
operations bpm/datapool sector 27,28 checkout |
Sereno |
Stored beam & injection |
|
Sunday, Oct. 2, 2016 |
|
|
0000-0300 |
Adjust timing/amplitude of kickers |
Emery |
Stored Beam & injection |
0300-0600 |
Orbit control tests ID6 (S6C:H1, V1) |
Emery |
Stored Beam & injection |
0600-1200 |
IEX checkout |
Xiao |
Stored Beam & injection |
1200-1800 |
S6 & S35 XBPM comissioning |
Sereno, Yang |
Stored beam & injection |
1800-2200 |
Lattice for better vertical dynamic aperature |
Emery |
Stored beam & injection |
2200-2400 |
CPU checkout 2 |
Xiao |
Stored beam & injection |
|
Monday, Oct. 3, 2016 |
|
|
2400-0400 |
CPU Checkout 2 (continued) |
Xiao |
Stored beam & injection |
0400-1000 |
Top-up verification |
OPS |
Stored beam & injection |
1000-1400 |
Booster access to remove attenuator for BTX MBA kicker to outside of tunnel. Booster studies with beam continue after, access, occasional injection possible |
Yao, P.S. Group |
No injection during Booster Access/Occ. injection after |
1000-1200 |
Test APS-U CMPSI-2 installed in S27/28. (OPS to condition those correctors when test complete |
Fors |
No beam |
1300-1500 |
commissioning of the integrated beam stability system in Sectors 27/28 |
Carwardine, Sereno, et al |
Stored beam & injection |
1500-1600 |
Beam dump test, ID6 SCU off and powered, with abort kicker |
Sajaev |
Stored beam & injection |
1600-1800 |
Final Lattice setup |
Sajaev |
Stored beam & injection |
1800-2200 |
Final pinhole camera and bunch purity set-up |
Yang |
Stored beam & injection |
2300-2400 |
Continue final Lattice setup |
Sajaev |
Stored beam & injection |
|
Tuesday, Oct. 4, 2016 |
|
|
0000-03000 |
Continue final Lattice setup(continued) |
Sajaev |
Stored beam & injectio |
0300-0630 |
OPEN |
|
|
0630-0800 |
Prepare for user beam |
OPS |
Stored beam & injection |