Schedule for Run03-1, 2016 (includes Pre-studies)

Sep 23rd 0800 – Oct. 4th 0800

Time

Descriptions

Studiers

SR Status


Fri, Sep 23, 2016 (Pre-Studies)



0800-1000

MPS validations, final checkout

Smith


1200-1400

Establish injection.

Schroeder,

Sajaev

Stored Beam & Injection

1400-1600

Aperture scan, ID6 SCU(18-2) chamber, 15 mA in many bunches.

Emery, Sajaev

Stored Beam & Injection

1600-2000

Beam-based alignment, ID6 and ID1 scan, 24 bunches < 25 mA.

Harkay

Stored Beam & Injection

1700-1900

Realign ID6 SCU chamber if needed (could be postponed to Mon, Sep 26). not needed

Jansma et al.

Access Zone A

2000-2300

Beam-based alignment, BM6 scan, 324 bunches < 25 mA.

Harkay

Stored Beam & Injection

2300-2400

Rf conditioning, 115 mA, 24 bunches.

Measure x,y tunes at intervals of 5 mA.

No P0 FB.

OPS

Stored Beam & Injection


Sat, Sep 24, 2016 (Pre-studies)



0000-1500

Rf conditioning, 115 mA, 24 bunches.

Measure x,y tunes at intervals of 5 mA.

No P0 FB. NOT COMPLETED

OPS

Stored Beam & Injection


STUDIES DELAYED




Sun, Sep 25, 2016 (Pre-studies)




STUDIES DELAYED




Mon, Sep 26, 2016 (Pre-studies)




STORAGE RING STUDIES DELAYED



0800-1500

Set up match on RG2 and files for RG1

Pasky, Yine Sun

Limited injection

1300-1400

Access Booster to check attenuator for BTX MBA kicker

Yao, Keane

No Booster beam

1500-1700

Check-out BTX MBA kicker (no steering)



1500-2400

Troubleshooting elevated vacuum at L5




Tuesday, Sep 27, 2016 (Pre-studies end at 08:00)



0000-2400

All Studies Delayed. Troubleshooting/replacing window/conditioning at L5




Wednesday, Sep 28, 2016



0000-2400

All Studies Delayed. Troubleshooting/replacing window/conditioning at L5




Thursday, Sep 29, 2016



0000-1000

All Studies Delayed. Troubleshooting/replacing window/conditioning at L5



1000-1600

Get beam through injectors



1600-2400

Rf conditioning, 115 mA, 24 bunches.

Measure x,y tunes at intervals of 5 mA.

No P0 FB.

OPS

Stored beam & injection


Friday, Sep 30, 2016



0000-0500

Rf conditioning, 115 mA, 24 bunches.

Measure x,y tunes at intervals of 5 mA.

No P0 FB.

OPS

Stored beam & injection

0500-0700

Accumulate 100 mA, 24 bunches, ID6 SCU powered

Sajaev

Stored beam & injection

0700-1100

BPLD Validations

Erwin

Stored Beam & Injection

1100-1400

X-ray BPM sanity check

Hahne

Stored Beam & Injection

1100-1400

Initial Pinhole camera setup

Yang

Stored Beam & Injection

1400-1600

Set-up P0 feedback

Yao

Stored Beam & injection

1600-1800

BPM offset measurements

Xiao

Stored Beam & injection

1800-2200

Orbit recovery

Xiao

Stored Beam & injection

2200-2400

S27 Grid X-ray BPMs commissioning

Sereno, Yang

Stored beam & injection


Saturday, Oct. 1, 2016



0000-0200

S27 Grid X-ray BPMs commissioning

Sereno, Yang

Stored beam & injection

0200-0600

Beam perturbation and field integrals test for ID6 SCU, check out skew quad FF

Emery/Sajaev

Stored Beam & Injection

0600-1000

Quench test, ID6 SCU powered

Emery

Stored Beam & Injection

1000-1600

CPU checkout I

Xiao

Occ injection.

1000-1600

Possible Booster study TBA (not high charge)

Calvey

Occ. injection possible

1600-2000

S27 XBPM commissioning

Sereno, Yang

Stored beam & injection

2000-2400

operations bpm/datapool sector 27,28 checkout

Sereno

Stored beam & injection


Sunday, Oct. 2, 2016



0000-0300

Adjust timing/amplitude of kickers

Emery

Stored Beam & injection

0300-0600

Orbit control tests ID6 (S6C:H1, V1)

Emery

Stored Beam & injection

0600-1200

IEX checkout

Xiao

Stored Beam & injection

1200-1800

S6 & S35 XBPM comissioning

Sereno, Yang

Stored beam & injection

1800-2200

Lattice for better vertical dynamic aperature

Emery

Stored beam & injection

2200-2400

CPU checkout 2

Xiao

Stored beam & injection


Monday, Oct. 3, 2016



2400-0400

CPU Checkout 2 (continued)

Xiao

Stored beam & injection

0400-1000

Top-up verification

OPS

Stored beam & injection

1000-1400

Booster access to remove attenuator for BTX MBA kicker to outside of tunnel. Booster studies with beam continue after, access, occasional injection possible

Yao, P.S. Group

No injection during Booster Access/Occ. injection after

1000-1200

Test APS-U CMPSI-2 installed in S27/28. (OPS to condition those correctors when test complete

Fors

No beam

1300-1500

commissioning of the integrated beam stability system in Sectors 27/28

Carwardine, Sereno, et al

Stored beam & injection

1500-1600

Beam dump test, ID6 SCU off and powered, with abort kicker

Sajaev

Stored beam & injection

1600-1800

Final Lattice setup

Sajaev

Stored beam & injection

1800-2200

Final pinhole camera and bunch purity set-up

Yang

Stored beam & injection

2300-2400

Continue final Lattice setup

Sajaev

Stored beam & injection


Tuesday, Oct. 4, 2016



0000-03000

Continue final Lattice setup(continued)

Sajaev

Stored beam & injectio

0300-0630

OPEN



0630-0800

Prepare for user beam

OPS

Stored beam & injection