Machine Studies
Draft Schedule for Run03-11, 2016
December 19th 0800 – December 20th 0000
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, December 19, 2016 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
L2 scope calibration and power monitor work |
Smith |
No Impact |
0810-1000 |
sddscontrollaw with filter (simth predictor) |
Emery, Shang |
Stored beam & occ. inj |
1000-1400 |
Change rf station water temperatures and measure beam with Dimtel instrumentation |
Harkay, Emery, Berenc, Wienands, Nassiri |
Stored beam & inj. |
1400-1600 |
Realign S27 ID GRID and test GRID interpolation software |
Yang |
Stored beam & inj. |
1600-2200 |
IBS studies sector 27 |
Sereno, et al |
Stored beam & occ. inj. |
2200-2400 |
Gentle shutdown of storage ring |
OPS |
No Beam |
|
Tuesday, December 20, 2016 |
|
|
0000-0600 |
LOTO and prepare for opening of Storage Ring and Booster |
OPS/FMS/HP |
No Beam |
0800-2400 (Wednesday) |
Linac conditioning |
RF Group |
No Injection |
|
Thursday, December 22, 2016 |
|
|
0000-0730 |
Linac conditioning |
RF Group |
No Injection |
0800-0810 |
Linac open for access |
OPS/HP |
|
|
|
|
|