Machine Studies

Draft Schedule for Run03-6, 2016

November 7th 0800 – November 8th 0800



Time

Descriptions

Studiers

SR Status


Monday, November 7, 2016



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Swap out SR Zone A sextupole converters

Ackley

No Beam

0930-1130

Investigate S40B:V4

Vargas

No Beam

0930-1130

Test calibration of L1 ss amplifier

Ma

No Beam

0930-1130

Switch to PAR RF back-up systems

RF Group

No injection

0930-1130

Check connectors on RF2

RF Group

No beam

0930-1130

Check blower on RF4 klystron garage

RF Group

No beam

0930-1130

Check for nitrogen leak on RF5 T/R set

RF Group

No injection

1000-1030

Remove parts from Zone A

Zientek

Access Zone A

1000-1100

Check bellows & endbox at 4-ID upstream location

Morrison

Access Zone A

1130-1200

Recover injectors/SR

OPS

Stored beam & injection

1200-2400

Investigate SR injection efficiency & lifetime

Sajaev, Emery, Xiao, Borland

Stored beam & injection


Tuesday, November 8, 2016



0000-0700

Investigate SR injection efficiency & lifetime (continued)

Sajaev, Emery, Xiao, Borland

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection