Draft Schedule for Run01-1, 2017
January 24th 0800 – January 31st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, January 24, 2017 |
|
|
0000-1800 |
RF conditioning with beam (12 hours) |
OPS |
Stored Beam& Injection |
|
BPM/feedback system checkout (parasitic) |
Sereno |
|
1800-2200 |
BPLD validations |
Erwin |
Stored Beam& Injection |
2200-2400 |
X-ray BPM sanity check |
Hahne |
Stored Beam& Injection |
|
Wednesday, January 25, 2017 |
|
|
0000-0400 |
Initial lattice setup |
Sajaev |
Stored Beam& Injection |
0400-0900 |
Orbit recovery |
Xiao |
Stored Beam& Injection |
0900-1000 |
13BM PSS End-to-End test |
OPS |
No beam |
0900-1100 |
Repair/replace RG2 Control Power supply |
Puttkammer |
No injection |
0900-1000 |
Troubleshooting broken BPMs, S21A:P3, and S37A:P4. |
Bui |
No injection |
1000-1200 |
Switch to back-up PAR RF systems and switch back (1st hour without Linac beam) |
Goel |
No Booster injection |
1200-1400 |
BPM/feedback system checkout for libera bpms |
Sereno, Brill |
Stored Beam& Injection |
1400-1800 |
S27 Integrated beam stability studies |
Sereno, et al |
Stored Beam& Injection |
1800-2400 |
Set up 6 GeV Booster/SR for LFB study |
Emery, Sajaev, Xiao, Harkay, Calvey |
Stored Beam& Injection |
|
Thursday, January 26, 2017 |
|
|
0000-0400 |
SCU sector 6 field integral measurement |
Emery |
Stored Beam& Injection |
0400-0800 |
High beta lattice study |
Y-P Sun |
Stored Beam& Injection |
0800-1200 |
ID4 aperture full measurement |
Y-P Sun |
Stored Beam& Injection |
1200-1300 |
AK0 checkout |
Harkay, Dooling |
Stored Beam& Injection |
1300-1600 |
P0 feedback setup |
Sajaev |
Stored Beam& Injection |
1600-2200 |
Dimtel LFB study |
Harkay, Emery, Berenc, Wienands, Nassiri, Byrd, Teytelman |
Stored Beam& Injection |
2200-2400 |
Automated commissioning study |
Sajaev |
Stored Beam& Injection |
|
Friday, January 27, 2017 |
|
|
0000-0300 |
Automated commissioning study |
Sajaev |
Stored Beam& Injection |
0300-0600 |
Dynamic aperture measurement |
Sajaev |
Stored Beam& Injection |
0600-0800 |
Open |
|
|
0800-1200 |
S27 Integrated beam stability studies |
Sereno, et al |
Stored Beam& Injection |
1200-1600 |
Bring degassifier back on-line (all equipment using PW will be shut off, after which all PW pumps will be shut down before the degassifier is valved in) |
Swetin, Kailus, etc. |
No beam in any machine |
1200-1600 |
Booster Orbit control (contingent study if degassifier is not ready) |
Emery, Shang, Sereno, Harkay, Calvey |
Stored Beam& Injection |
1600-2200 |
Dimtel LFB study |
Harkay, Emery, Berenc, Wienands, Nassiri, Byrd, Teytelman |
Stored Beam& Injection |
2200-2400 |
PAR tuneup with 4 combinations of RF systems. (OPS will assist at with RF switch and initial setup) Booster tune-up Booster 10 nC study |
Harkay/Calvey |
Stored Beam& Injection |
|
Saturday, January 28, 2017 |
|
|
0000-0400 |
PAR tuneup with 4 combinations of RF systems. (continued) Booster tune-up Booster 10 nC study (OPS will LOTO BTS:BX p.s. in addition to any other high current requirements) |
Harkay/Calvey |
Stored Beam& Injection |
0200-1000 |
Open |
|
|
1000-2400 |
CPU checkout |
Xiao |
Limited Injection |
|
Sunday, January 29, 2017 |
|
|
0000-0800 |
Top-up verification |
OPS |
Stored Beam & Injection |
0800-1600 |
Sector 27 XBPM2 commissioning (shutters open) |
Sereno, Yang |
Stored Beam & Injection |
1600-2400 |
IEX checkout |
Xiao |
Limited Injection |
|
Monday, January 30, 2017 |
|
|
0000-0700 |
Top-up verification |
OPS |
Stored Beam & Injection |
0700-1200 |
Final lattice and injection setup |
Sajaev |
Stored Beam & Injection |
1200-1400 |
SCU6 skew quad FF checkout |
Harkay |
Stored Beam & Injection |
1400-1600 |
Final pinhole & bunch purity set-up |
Yang |
Stored Beam & Injection |
1600-2400 |
Sector 6 and 36 GRID Xbpm testing |
Sereno, Yang |
Stored Beam & Injection |
|
Tuesday, January 31, 2017 |
|
|
0000-0230 |
Final orbit checkout |
Xiao |
Stored Beam & Injection |
0230-0630 |
ID4 local impedance measurement |
Sajaev |
Stored Beam& Injection |
0630-0800 |
Prepare for user Operations (24 singlets – Top-Up) |
Ops |
Stored Beam & Injection |