Draft Schedule for Run01-10, 2017

April 3rd 0800 – April 4th 0800



Time

Descriptions

Studiers

SR Status


Monday, April 3, 2017



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1030

Test kicker timeout DB changes reboot iocinjtime iocmtime

Fors

No Beam/No Injection

0930-1130

Swap out sextupoles for upgrade

Vargas

No Beam

0930-1130

Investigate S25A:H3

Vargas

No Beam

0930-1130

Swap S9A:H3

Jordan

No Beam

1030-1230

PAR PEM testing

Soliday/Pasky

No Injection

1130-1230

Abort kicker checks

Schroeder/Wang

No Beam

1230-1300

Recover SR and injectors (324)

OPS

Stored Beam & Injection

1300-1700

S27 Integrated Beam Stability Studies

Sereno, et al.

Stored Beam & Injection

1700-2100

Measure and vary chromaticity in PAR

Calvey/Sereno/Dooling

No Injection

2100-2400

Adjust BTS trajectory in SR

Emery

Stored Beam & Injection


Tuesday, April 4, 2017



0000-0700

24-ID Compton XBPM study

Yang

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection