Machine Studies
Draft Schedule for Run01-12, 2017
April 17th 0800 – April 18th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, April 17, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Swap swsr12 module |
Westbrook |
Stored Beam & Injection |
0930-1130 |
Swap out sextupoles for upgrade |
Vargas |
No Beam |
0930-1130 |
Thermal scan SR converters Zone D |
Puttkammer |
No Beam |
1000-1100 |
Replace S38 cavity blower |
Wright |
Access Zone F |
1000-1200 |
Laser alignment |
Dooling |
Access Linac |
1200-1230 |
Recover SR and Injectors (324) |
OPS |
Stored Beam & Injection |
1230-1630 |
S27 integrated beam stability studies |
Sereno, et al. |
Limited Injection |
1230-1630 |
BTX kicker studies |
Carwardine, et al. |
Limited Injection |
1630-2030 |
PAR high charge study |
Harkay/Calvey/Dooling |
Limited Injection |
1630-2030 |
24-ID Comptom XBPM (Shutter permit needed) 6-ID GRID XBPM study(Shutter permit removed) |
Yang |
Stored Beam & Injection |
2030-2400 |
Mombo data collection |
Hahne/Shang |
Stored Beam & Injection |
|
Tuesday, April 18, 2017 |
|
|
0000-0200 |
RG1 beam study |
Y.E. Sun |
No Injection |
0200-0700 |
HSCU lattice with low chromaticity |
Sajaev/Y.P. Sun |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |