Machine Studies
Draft Schedule for Run01-13, 2017
April 25th 0000 – April 26th 0000
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, April 25, 2017 |
|
|
0000-0010 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0010-0400 |
Setup HSCU |
Sajaev |
Stored Beam & Injection |
0400-0800 |
Booster orbit correction and BPM measurement |
Calvey/Emery/Shang |
No Injection |
0800-1000 |
Install and test BTS:RSR |
Vanis |
No Injection |
1000-1400 |
24-ID Compton XBPM and 6-ID GRID XBPM study |
Yang |
Limited Injection |
1400-1800 |
S27 Integrated Beam Stability Study |
Carwardine, et al. |
Limited Injection |
1000-1800 |
BTX Kicker measurement |
Carwardine/Wang/Sun/Xiao |
Limited Injection |
1800-2200 |
Prepare orbit for next run |
Xiao |
Stored Beam & Injection |
2200-2400 |
Gentle shutdown |
OPS |
No Beam |