Machine Studies
Draft Schedule for Run01-6, 2017
March 6th 0800 – March 7th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 6, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
SCU functional tests |
Smith |
No Beam |
0930-1030 |
Install booster bpm database |
Pietryla |
Limited Injection |
0930-1130 |
Swap out sextupoles for upgrade |
Vargas |
No Beam |
0930-1130 |
Modify LTP:Q10 & L1:RG1:QM4 |
Donkers |
No Injection |
0930-1130 |
Swap S40 quads |
Puttkammer |
No Beam |
1000-1200 |
Troubleshoot PTB triple stop |
Gagliano |
Access PAR |
1200-1230 |
Recover SR (inject 324) |
OPS |
Stored Beam & Injection |
1230-1830 |
Integrated beam stability study |
Sereno et al. |
Limited Injection |
1230-1530 |
Booster orbit correction |
Sajaev/Emery/Shang |
Limited Injection |
1530-1830 |
Booster tuning studies |
Harkay/Calvey |
Limited Injection |
1830-2130 |
1 Hz PAR beam size measurement |
Calvey/Sereno/Brill |
No Injection |
1830-2130 |
Test ID FF (324) |
Emery/Shang |
No Injection |
2130-2400 |
On-axis injection to small DA optics |
Xiao |
Stored Beam & Injection |
|
Tuesday, March 7, 2017 |
|
|
2400-0300 |
On-axis injection to small DA optics |
Xiao |
Stored Beam & Injection |
0300-0700 |
High beta lattice study |
Yipeng Sun |
Stored Beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |