Machine Studies
Draft Schedule for Run02-4, 2017
June 19th 0800 - June 20th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 19, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Install noise suppression capacitors RF-5 |
RF Group |
No Injection |
0930-1130 |
Take output bridge current measurements |
Vargas |
No Beam |
0930-1130 |
Swap sextupoles for upgrades |
Ackley |
No Beam |
0930-1130 |
Increase the Current Gain in the Booster ramp converter B3C0H by 20% to 25% |
Donkers |
No injection |
1130-1200 |
Recover injector/storage-ring |
OPS |
Stored Beam & injection |
1200-1400 |
measure Booster efficiency vs gap voltage at injection with up to 6 nC beam |
Yao |
Occasional inj. possible |
1200-1500 |
Testing closed-loop response matrix measurements in sector 27 (324 singlets) |
Sereno/Carwardine |
Stored beam |
1500-1800 |
BPLD validation script development |
Sereno/Shang |
Stored beam & injection |
1800-2000 |
add more bpms to XRDP |
Sereno |
Stored beam & injection |
2000-2330 |
Compton XBPM studies in sector 26 |
Yang |
Stored beam & injection |
2330-2400 |
Response Matrix accuracy study |
Sajaev |
Stored beam & injection |
|
Tuesday, June 20, 2017 |
|
|
0000-0300 |
Response Matrix accuracy study (continued) |
Sajaev |
Stored beam & injection |
0300-0700 |
ID orbit switching |
Xiao |
Stored beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |