Machine Studies
Schedule for Run02-5, 2017
June 26th 0800 - June 28th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, June 26, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Adjust flow meter trip settings B:ES2 |
Vanis |
No Injection |
0930-1130 |
Swap sextupoles for upgrades |
Ackley |
No Beam |
0930-1200 |
Install and test LRF databases |
Pietryla |
Limited Injection |
1200-1400 |
Optimize PAR/Booster rf frequency ramp. Need to change rf frequency |
Yao, Lenkszus |
No Beam |
1400-1500 |
test Booster B3C0H with modified shunts with beam |
Yao, Hillman, Shang |
No injection |
1500-2100 |
hybrid setup with proper chromaticity and injection optimization |
Emery, Xiao, Yao |
Stored beam and injection |
2100-2400 |
Orbit switch |
Xiao |
Stored beam and injection |
|
Tuesday, June 27, 2017 |
|
|
0000-0100 |
Orbit switch |
Xiao |
Stored beam & injection |
0100-0300 |
PAR operator training (23-07) |
Christensen/ Smith |
Limited Injection |
0300-0800 |
OPEN |
|
|
0800-1000 |
Linac RF recovery script testing |
Yine Sun |
Stored beam |
1000-1200 |
Abort kicker check-out |
Harkay |
Stored beam & injection |
1200-1700 |
Booster on-momentum studies (no storage ring beam, rf freq change |
Harkay, Calvey, Berenc, Emery, Yao |
No beam |
1700-2200 |
Booster high charge studies, investigate limit, characterize beam |
Harkay, Calvey, Berenc, Yao |
Stored beam |
2200-2400 |
Sector 26 Compton XBPM testing |
Yang |
Stored beam & injection |
|
Wednesday, June 28, 2017 |
|
|
0000-0400 |
Sector 26 Compton XBPM testing (continued) |
Yang |
Stored beam & injection |
0400-0600 |
PAR operator training (23-07) |
Christensen/ Smith |
Limited Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |