Draft Schedule for Run02-8, 2017
July 17th 0800 – July 18th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 17, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving PS |
PS Group |
No Injection |
0930-1130 |
Test IEX software |
Smith |
No Beam |
0930-1130 |
Investigate RF-4 keystroke window blowers |
RF Group |
No Beam |
0930-1130 |
Swap out SR sextupoles |
Ackley |
No Beam |
0930-1130 |
Take output bridge I measurements Zone B & D |
Jordan |
No Beam |
1000-1100 |
Change temperature sensors |
Erwin |
Access Zone A |
1000-1100 |
Replace Booster C4 tuner piston #1 thermocouple |
RF Group |
Access Booster |
1130-1200 |
Recover injectors/storage-ring |
OPS |
Stored beam & injection |
1200-1500 |
Booster dispersion and chromaticity measurement. Need to change rf frequency |
Yao, Shang |
No Beam |
1500-1800 |
BPLD validation script testing |
Sereno |
Stored beam & injection |
1800-2200 |
Integrated beam stability studies in sector 27 |
Sereno |
Stored beam & injection |
2200-2400 |
sector 26 compton XBPM studies |
Yang |
Stored beam & injection |
|
Tuesday, July 18, 2017 |
|
|
0000-0300 |
sector 26 compton XBPM studies |
Yang |
Stored beam & injection |
0300-0700 |
beam lifetime measurement |
Xiao |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |