Machine Studies

Draft Schedule for Run03-3, 2017

October 16th 0800 – October 17th 0800



Time

Descriptions

Studiers

SR Status


Monday, October 16, 2017



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1000

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

1000-1200

PAR 40° compensation phase shifter tests

T. Smith

Limited Injection

1000-1300

Shutdown EMCC X1-9 to repair bucket for exhaust fan for 33-ID-E

Kailus

No Beam

1000-1200

Booster console exam

Smith/Pasky

Parasitic to PSR studies

1030-1130

Remove TLDs at S27

Dombrowski

Acces Zone D

1200-1400

Linac power control law testing

Pasky/Soliday

Limited Injection

1000-1400

Booster Energy Saver Software Test

Control

No Beam

1400-1430

SR recovery

OPS

Stored Beam & Injection

1430-1630

Interleaving with SR topup

Y. Sun et al

Stored Beam & Injection

1600-1700

SR corrector feed forward test

H. Shang/L. Emery

Stored Beam & Injection

1700-1900

PAR vertical beam size measurement with streak camera

C. Yao/B. Yang/ J. Calvey/D. Hui

Limited injection

1900-2100

Booster BM bdot coils signal measurement

C. Yao/T. Puttkammer

No Beam

2100-2400

Injection into small DA machine

A. Xiao

Stored Beam & Injection


Tuesday, October 17, 2017



0000-0300

Chracterize 6 GeV lattice

L.Emery

Stored Beam & Injection

0300-0600

ID feedforward characterization

L. Emery

Stored Beam & Injection

0600-0700

SCU1 checkout

L. Emery

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection