Machine Studies
Draft Schedule for Run03-5, 2017
October 30th 0800 – November 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 30, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Investigate loss of magnet setpoints on ioclirfgun |
Pietryla |
No Injection |
0930-1030 |
Shut off SRVC 2 pump skid for inspection |
Wright |
No beam |
0930-1130 |
Investigate loss of communication with Sector 13 cabinet 4 |
Jordan |
No Beam |
0930-1130 |
Turn on control power BSD-U PS and verify controls |
Puttkammer |
Limited Injection |
0930-1130 |
Swap out SR quad converters Zone F |
Vargas |
No Beam |
1100-1300 |
Voltage measurement on PAR BPMs |
Wienads/ Brill et al |
PAR Beam |
0930-1330 |
Waveguide switch to RF-3 providing Booster |
RF Group |
No Beam/Injection possible after 1030 |
1330-1400 |
SR recovery |
OPS |
Stored Beam & Injection |
1400-1500 |
Test tune measurement on different bunch current |
Sereno/Brill/Sajaev |
Stored Beam & Injection |
1500-1700 |
Response matrix measurement |
Sereno/Shang/Sajaev |
Stored Beam & Injection |
1700-2100 |
Setup hybrid |
Sajaev |
Stored Beam & Injection |
2100-2300 |
SR training |
E. Smith |
Stored Beam & Injection |
2300-2400 |
Open |
|
|
|
Tuesday, October 31, 2017 |
|
|
0000-0700 |
Open |
|
|
0700-0800 |
Prepare for bus tie work |
OPS |
No beam |
0800-1400 |
Install bus tie for work one 13.2 kV feed to APS -- All Bldg. 420 RF systems off, Booster main ramping supplies and SR P.S. off |
Janik |
No beam |
0800-1000 |
PAR streak camera timing investigation |
Lenkszus/Yao |
No Beam |
1000-1200 |
Voltage measurement on PAR BPMs (continued) |
Wienads/ Brill et al |
PAR Beam |
1200-1400 |
PC Gun beam study |
Sun/Shang |
Limited Injection |
1400 |
Remove bus tie |
|
|
1400-1600 |
Topup interleaving study (need SR in top-up mode) |
Sun/Shang |
Stored Beam & Injection |
1600-1900 |
ID7 vertical aperture measurement |
Emery/Sun |
Stored Beam & Injection |
1900-2200 |
ID feedforward reproducibility |
Emery |
Stored Beam & Injection |
2200-2400 |
Orbit Switch |
Sajaev |
Stored Beam & Injection |
|
Wednesday, November 1, 2017 |
|
|
0000-0200 |
Orbit Switch |
Sajaev |
Stored Beam & Injection |
0200-0600 |
Slow freq beam motion study |
Sajaev |
Stored Beam & Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |