Machine Studies
Draft Schedule for Run03-8, 2017
November 22nd 0800 – November 24th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Wednesday, November 22, 2017 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1030 |
Switch over pumps 515 and 509 to standby pumps |
Wright |
No Beam |
0930-1130 |
Repair fiber connection for S8/9 |
Pruitt |
Stored Beam & Injection |
0930-1130 |
PAR APS-U LLRF installation, change PAR RF-12 AGC setpoint |
Berenc/RF Group |
Limited Injection |
0930-1130 |
Swap BS2 quadrupole converters Zone E |
Ackley |
No Beam |
0930-1130 |
Modify Zone F interlock racks |
Vargas |
No Beam |
0930-1130 |
Upgrade GesADC board PAR/Booster |
Donkers |
No Injection |
0930-1130 |
Test Booster 1Hz 2048 pt V-ref |
Yao, Shang |
No Injection |
1000-1030 |
Non beam portion of SR Requalification |
Schroeder/ Fystro |
No injectio |
1030-1100 |
Non-beam portion of SR Requalification |
Schroeder/ Christensen |
No injection |
1130-1330 |
Install ULM112 in iocbramp |
Fors |
No Injection |
1130-1330 |
Test Booster SD-U software |
Yao, Fors |
No Injection |
1330-1400 |
Recover SR (all normal orbit control, gaps open, make regular save) |
OPS |
Stored beam & injection |
1400-1800 |
Slow beam motion measurement |
Sajaev |
Stored beam & injection |
1800-2200 |
Test Booster local steering program |
Yao/Shang |
Limited Injection |
2200-2400 |
Beam test of 1Hz mode 2048 Booster ramp |
Yao |
No Injection |
|
Thursday, November 23, 2017 |
|
|
0000-0500 |
BTS measurement |
Xiao |
Stored beam & injection |
0500-0800 |
Open |
|
|
0800-1200 |
Top-up interleaving study |
Sun/Shang/ Keane |
Stored beam & injection |
1200-1500 |
Align PC gun beam through the linac and record stability in the booster bypass |
Dooling |
No injection |
1500-2200 |
Open |
|
|
2200-2300 |
SR Requalification test |
Schroeder/ LaBuda |
Stored beam & injection |
2300-2400 |
SR Requalification test |
Schroeder/ Ronzhin |
Stored beam & injection |
|
Friday, November 24, 2017 |
|
|
0000-0400 |
Current vs BPM sum signal calibration |
Sajaev |
Stored beam & injection |
0400-0600 |
Open |
|
|
0600-0700 |
SR Requalifcation test (0000-0700) |
Ronzhin/ Mazzio |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |