Machine Studies

Draft Schedule for Run03-9, 2017

December 4th 0800 – December 5th 0800



Time

Descriptions

Studiers

SR Status


Monday, December 4, 2017



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1030

Upgrade Booster RF power monitor

DiMonte

No Injection

0930-1130

Modify Zone F interlock racks

Vargas

No Beam

0930-1130

Upgrade GesADC for Booster Gespacs

Donkers

Limited Injection

0930-1130

Swap quadrupole converters Zone E

Ackley

No Beam

0930-1130

Swap and validate LTP BESOCM

Keane

No Injection

0930-1130

Invesitgate PC Gun/Laser timing jitter

Pietryla

Limited Injection

0930-1130

Test B:SD-U/SD switching pem

Yao/Shang

No Beam

1100-1130

SR requalification (part 1)

Bogdan/

Schroeder

No Beam

1130-1200

Recover SR beam/make open gaps saves

OPS

Stored Beam & Injection

1200-1300

SR requalification (part 2)

Bogdan/

Schroeder

Stored Beam & Injection

1300-1400

Measure Quad hysteresis with tune measurement

Emery

Stored Beam & Injection

1300-1500

Interleaving topup study

Sun/Shang

Stored Beam & Injection

1500-2000

ID4 local impedance measurement

Sajaev

Stored Beam & Injection

2000-2400

Orbit Switch

Xiao

Stored Beam & Injection


Tuesday, December 5, 2017



0000-0600

XBPM noise study

Sereno/Yang/ Hahne

Stored Beam & Injection

0600-0700

SR requalification (23:00-07:00)

Angel/LaBuda

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection