Machine Intervention

Schedule for Run1-0, 2018

(includes Pre-Studies)

January 19th 0800 – January 30th 0800



Time

Descriptions

Studiers

SR Status


Friday, January 19, 2018 (pre-studies)



0800-1000

MPS validations, final checkout

Smith, OPS

No Beam

1000-1200

Establish injection

Emery, Schroeder

Stored beam & injection

1200-1300

BPLD validation for 7-ID <25 mA (requires HSCU to be on at 0A)

Erwin

Stored beam & injection

1300-1500

Aperture scan, HSCU chamber, 15 mA in multiple bunches

Emery, Sajaev

Stored beam & injection

1500-1900

Scan beam ID7 in x&y, 24 bunches < 25 mA.

Yipeng Sun

Stored beam & injection

1600-1800

Realign HSCU chamber if needed

Jasma, et al

Access Zone A

1900-2400

Rf conditioning, 115 mA, 24 bunches. Pause for 1 hr at 100mA. Measure x,y tunes at intervals of 5 mA. No P0 FB.

OPS

Stored beam & injection


Saturday, January 20, 2018 (pre-studies)



0000-1200

Rf conditioning, 115 mA, 24 bunches. Pause for 1 hr at 100mA. Measure x,y tunes at intervals of 5 mA. No P0 FB.

OPS

Stored beam & injection

1200-1400

HSCU powered 102 mA 24 bunches Emery

Emery

Stored beam & injection

1400-1500

Beam dump

Emery, Yipeng Sun

Stored beam & injection

1500-1800

102 mA 324 bunches

Operators

Stored beam & injection

1800-2400

OPEN (Maintain 100mA if no studies)




Sunday, January 21, 2018 (pre-studies)



0000-0900

OPEN (Maintain 100mA if no studies)



0900-1200

Field integrals 324 bunches 102mA

Emery, Yipeng Sun

Stored beam & injection

1200-1400

Quench test

Harkay, Emery, Yipeng Sun

Stored beam & injection

1400-2400

OPEN (Maintain 100mA if no studies)




Monday, January 22, 2018 (pre-studies)



0000-0800

OPEN (Maintain 100mA if no studies)



0800-1400

Set up injectors for 425MeV

Yine Sun, Pasky, Harkay

Occ. injection possible

0800-1200

Initial BPM checkout

Sereno

Stored beam & occ. inj.

1200-1400

Initial pinhole camera set-up

Yang

Stored beam & occ. inj.

1400-1600

Check motion with 0.5mA and no VC water.

Emery

Stored beam & injection

1600-1800

Check noise on trims and P0 initial feedback setup

Emery

Stored beam & injection

1800-2100

ID7 aperature measurement

Yipeng Sun

Stored beam & injection

2100-2400

Initial lattice set-up

Sajaev

Stored Beam & injection


Tuesday, January 23, 2018



0000-0800

OPEN (maintain 100mA if no studies)



0800-1200

BPLD validations

Hahne

Stored beam & injection

1200-1600

X-ray BPM Sanity check

Hahne

Stored beam & injection

1600-2100

Injection tune-up

Sajaev

Stored beam & injection

2100-2300

BPM offset measurement

Xiao/Emery

Stored beam & injection

2300-2400

Orbit recovery

Xiao/Emery

Stored beam & injection


Wednesday, January 24, 2018



0000-0200

Orbit recovery

Xiao/Emery

Stored beam & injection

0200-0800

425 MeV tuneup and high-charge measurements

Harkay, Calvey, Yao

Occ. injection possible

0800-0900

Interleaving top-up checkout (SR needs to be available for top-up

Yine Sun, Shang

Stored beam & injection

0900-1100

Interleaving procedure testing/training

Yine Sun, Pasky, etc.

Stored beam & injection

1100-1600

Better steering for HSCU, 7BM

Emery

Stored beam & injection

1600-1900

Accumulation limit for hybrid mode

Emery

Stored beam & injection

1900-2300

ID4 aperature measurement

Emery

Stored beam & injection

2300-2400

PAR studies

Calvey

No injection


Thursday, January 25, 2017



0000-0300

PAR studies (continued)

Calvey

No injection

0300-0800

OPEN



0800-1100

BESOCM and Linac waveguide switching validation

Pietryla, Pasky

No Injection

0800-1100

Continue P.S. testing

Iftikhar

No beam

0800-1200

Booster SDU study

Yao, Shang, Puttkammer

Limited injection

0800-1400

RF3 supplying Booster waveguide switch to RF3/RF4

RF Group

Limited injection

0800-1100

S6 SCU training

Kasa

No beam

1100-1200

Restore S6C:V1 P.S.

Puttkammer

No beam

1100-1300

SF6 system maintenance

Michalek

Limited injection

1400-2000

425-MeV tuneup and high-charge measurements (fill ring before)

Harkay, Calvey, Yao

Limited injection

1400-2000

S7 HSCU commissioning at beamline (shutter permit needed)

S7 (Walko)

Stored beam

2000-2400

Verify 6GeV SR setup

Emery

Stored beam & injection


Friday, January 26, 2018



0000-0700

Comissioning simulation testing (cont.)

Sajaev

Stored beam & injection

0700-1100

Laser alignment

Dooling

Linac Access

1100-1300

PC gun bean in linac checkout (including waveguide switching)

Yine Sun, Dooling

Stored beam

1300-1700

S7 HSCU commissioning at beamline with Top-up (shutter permit needed)

S7 beamline (Walko]

Stored beam & injection

1700-2100

Booster steering studies

Yao

Limited injection

2100-2400

425MeV tuneup and high charge studies

Harkay

Infrequent injection possible


Saturday, January 27, 2018



0000-0100

425MeV tuneup and high charge studies (continued)

Harkay

Infrequent injection possible

0100-0800

OPEN



0800-1600

CPU correction

Xiao/Emery

Stored beam & injection

1600-2400

Top-up verification

OPS



Sunday, January 28, 2018



0000-0800

Top-up verification

OPS


0800-1600

IEX correction

Xiao/Emery

Stored beam & injection

1600-2400

Top-up verification

OPS

Stored beam & injection


Monday, January 29, 2017



0000-0700

Top-up verification

OPS

Stored beam & injection

0700-1500

PAR RF1 absorptive filter test

Goel/Madden, Yao, Harkay, Calvey

Stored beam

0800-1200

Access into Zone A & F for VC chamber vibration measurements and installing shims

Emery, Preissner

No beam

1500-1800

Final pinhole camera set-up and bunch purity measurement set-up

Yang

Stored beam & injection

1800-1900

Final LIST phase tuning for bunch purity and PAR FF table setup (requires frequent injections & dumps into the SR)

Harkay

Stored beam & injection

1900-2400

PC Gun Studies

Yine Sun

Occasional injection available


Tuesday, January 30, 2017



0000-0100

OPEN



0100-0630

Final orbit checkout

Xiao/Emery

Stored beam & injection

0630-0800

Prepare for User Operations (24 singlets)

OPS

Stored beam & injection