Machine Studies
Draft Schedule for Run01-11, 2018
April 9th 0800 – April 10th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, April 9, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Replace intermittent flow detector at RF5 |
RF Group |
No Injection |
0930-1030 |
Inspect B:BM supply output filters |
Goetzen |
Limited Injection |
0930-1130 |
Upgrade iocbbpm3 to EPICS R3.14.12.5 |
Pietryla |
Limited Injection |
0930-1130 |
Swap quad converters |
Ackley/Vargas |
No Beam |
0930-1130 |
Measure RTFB DSP processing delay |
Xu |
No Beam |
1130-1300 |
SR console qualification |
Smith/Schroeder |
Stored Beam & Injection |
1300-1700 |
investigate Booster BM current ripple and optimize autoRampCorrection |
Yao, Shang |
Occ. Inj. possible |
1300-1700 |
orbit / rf phase feedback testing |
Sereno |
Stored beam & occ. inj. |
1700-2100 |
6 GeV studies |
Emery |
Stored beam & inj. |
2100-2400 |
Commissioning Script work |
Sajaev |
Stored beam & injection |
|
Tuesday, April 10, 2018 |
|
|
0000-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |