Machine Studies

Draft Schedule for Run01-12, 2018

April 16th 0800 – April 17th 0800



Time

Descriptions

Studiers

SR Status


Monday, April 16, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Hahne

Stored Beam & Injection

0930-1030

Replace harmonic load fan

Goel

No Beam

0930-1130

Upgrade iocbbpm3 to EPICS R3.14.12.5

Pietryla

Limited Injection

0930-1130

Thermal scan SR converters Zone D

Puttkammer

No Beam

0930-1130

Investigate Booster BM ramp ripples

Yao

Limited Injection

0930-1130

Swap out S5B:S2 P.S.

Puttkammer

No beam

0930-1130

Measure real time feedback DSP processing delay

S. Xu

No beam

1130-1200

Recovery or injectors and storage-ring

OPS

Stored beam & injection

1200-1600

Troubleshooting RF2 Klystron (24 singlets)

RF Group, OPS

Stored beam & injection

1300-1400

Test corrector punch down script

Shang, Schroeder

Stored beam

1600-2000

Orbit / rf phase feedback testing, and IBS PID design testing (324 singlets)

Sereno et al

Stored beam

2000-2400

Orbit switch

Xiao

Stored beam & injection


Tuesday, April 17, 2018



0000-0300

6 GeV BTS line.

Emery

No injection

0300-0600

Commissioning work

Sajaev

Stored beam & injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection