Machine Studies
Draft Schedule for Run01-12, 2018
April 16th 0800 – April 17th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, April 16, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Hahne |
Stored Beam & Injection |
0930-1030 |
Replace harmonic load fan |
Goel |
No Beam |
0930-1130 |
Upgrade iocbbpm3 to EPICS R3.14.12.5 |
Pietryla |
Limited Injection |
0930-1130 |
Thermal scan SR converters Zone D |
Puttkammer |
No Beam |
0930-1130 |
Investigate Booster BM ramp ripples |
Yao |
Limited Injection |
0930-1130 |
Swap out S5B:S2 P.S. |
Puttkammer |
No beam |
0930-1130 |
Measure real time feedback DSP processing delay |
S. Xu |
No beam |
1130-1200 |
Recovery or injectors and storage-ring |
OPS |
Stored beam & injection |
1200-1600 |
Troubleshooting RF2 Klystron (24 singlets) |
RF Group, OPS |
Stored beam & injection |
1300-1400 |
Test corrector punch down script |
Shang, Schroeder |
Stored beam |
1600-2000 |
Orbit / rf phase feedback testing, and IBS PID design testing (324 singlets) |
Sereno et al |
Stored beam |
2000-2400 |
Orbit switch |
Xiao |
Stored beam & injection |
|
Tuesday, April 17, 2018 |
|
|
0000-0300 |
6 GeV BTS line. |
Emery |
No injection |
0300-0600 |
Commissioning work |
Sajaev |
Stored beam & injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |