Machine Studies
Draft Schedule for Run01-3, 2018
February 12th 0800 – February 13th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 12, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
ACIS validate L6 |
OPS/RF Group |
No Injection |
0930-1000 |
Photograph Tcav area of Linac |
OPS/misc |
Access Linac |
0930-1030 |
Tighten BPLD card keyswitch in iocs5bpm (will be power cycled) |
Brill |
No beam |
0930-1130 |
Swap out quadrupoles |
Ackley |
No Beam |
0930-1130 |
Troubleshoot S6/7 canted correctors |
Jordan |
No Beam |
0930-1130 |
Replace F1 LED in SR IK4 |
Vanis |
No Beam |
1000-1100 |
Reboot injector BPM iocs |
Pietryla |
No Injection |
1000-1100 |
Test FFT software on iocbbpm3 |
Lenkszus |
No Injection |
1000-1500 |
Repair 33ID safety shutter |
Gagliano |
Access Zone E |
1100-1300 |
measure response and setup Booster injection controllaw with new FFT processes |
Yao/Lenkszuz |
Occ. injection possible |
1300-1500 |
test PTB beam optimization with the new linearized sum signal |
Yao |
Limited injection |
1500-1600 |
PAR Pem testing |
Calvey |
Limited injection |
1500-1600 |
Recover SR and verify injection/stored beam |
OPS |
Stored beam & injection |
1600-1630 |
BPLD validation of S4,5,6 ID |
Sereno |
Stored beam & injection |
1630-2000 |
XBPM gap scans and alignment testing |
Sereno |
Stored beam & injection |
2000-2400 |
check on 6 GeV lattice |
Emery |
Stored beam & injection |
|
Tuesday, February 13, 2018 |
|
|
0000-0100 |
Check on-one-side quadrupole scan for BPM offset |
Emery |
Stored beam |
0100-0700 |
TBD |
Xiao |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |