Machine Studies

Draft Schedule for Run01-4, 2018

February 19th 0800 – February 20th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 19, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0820

Make adjustment to circulator TCU for RF2 and monitor RF2 during gap scans

Goel

Stored Beam & injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno

Stored Beam & Injection

0930-1030

Swap out S13B:Q5

Vargas

No Beam

0930-1130

Swap out quadrupoles

Ackley

No Beam

0930-1130

Test S2/3 raw DB changes

Hillman/Xu

No Beam

0930-1130

Replace F1 LED in SR IK4

Vanis

No Beam

0930-1100

Install Linac RF DB changes

Pietryla

No Injection

0930-1130

Test run HSCU

Smith

No Beam

1100-1200

Measure Booster dispersion for LOCO study. Need to change rf frequency.

Yao

No beam

1200-1300

Test FFT software on iocbbpm3

Lenkszus

Limited Injection

1300-1500

Continue Booster injection controllaw setup after Lenkszus study

Yao

Occasional inj. possible

1300-1500

Make adjustments for RF2 with beam (may continue parasitically during the Sereno's study)

Goel

Stored beam & occ. injiction

1500-1830

XBPM alignment and gap scans

Sereno

Stored beam & injection

1830-2130

Injection efficiency dependence on BTS energy

Emery

Stored beam & injection

2130-2400

6 GeV lattice

Emery, Xiao

Stored beam & injection


Tuesday, February 20, 2018



2400-0100

6 GeV lattice (continued)

Emery, Xiao

Stored beam & injection

0100-0400

ID 4 impedance measurement

Sajaev

Stored Beam & injection

0400-0700

Commissioning simulation

Sajaev

Stored Beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection