Machine Studies

Draft Schedule for Run01-5, 2018

February 26th 0800 – February 27th 0800



Time

Descriptions

Studiers

SR Status


Monday, February 26, 2018



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Sereno, Schroeder

Stored Beam & Injection

0930-1130

Replace rack mounted power strip (may lose Metasys)

Smith, Pruitt

Stored Beam & Injection

0930-1030

Waveguide switch to SR RF2

RF Group

No beam

0930-1130

Swap out quadrupoles

Vargas

No Beam

0930-1130

Install Linac RF DB changes

Pietryla

Limited Injection

1030-1330

Test SRRF PEMs

Soliday/Schroeder

No Beam

1130-1330

Set-up PAR rf system manager files

Harkay

No injection

1330-1400

Recover SR

OPS

Stored Beam & injection

1400-1700

Finish gap scans and realign XBPMs

Sereno/Hahne

Stored Beam & Injection

1700-2100

Orbit switch

Xiao

Stored Beam & Injection

2100-2400

PAR high charge studies

Harkay

Occassional injection possible


Tuesday, February 27, 2018



0000-0500

PAR high charge studies (continued)

Harkay

Occassional injection possible

0500-0700

OPEN



0700-1000

PAR Loss Monitor studies

Dooling, Yao

Limited injection

0730-0800

Prepare for Zone A Access

OPS

Stored beam

0800-0900

Inspect HSCU cold heads for leak

Hasse

Zone A Access

0830-1000

Switch back to SR RF3 if needed (RF Group will make the decision)

RF Group

No beam

1000-1200

optimize PTB matching

Yao

Limited injection

1200-1400

optimize Booster efficiency with local steering

Yao, Shang

Limited injection

1400-1800

6 GeV lattic

Emery, Xiao

Stored beam & injection

1800-2200

BTS line measurement

Xiao

Stored beam & injection

2200-2400

P1 BPM offset measurement

Xiao

Stored Beam & Injection


Wednesday, February 28, 2018



0000-0630

Local impendance and/or commissioning simulation

Sajaev

Stored Beam & injection

0630-0800

Prepare for User beam

OPS

Stored Beam & Injection