Draft Schedule for Run01-7, 2018
March 12th 0800 – March 13th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, March 12, 2018 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0815 |
Transfer orbit, make saves, send beam to dump and install save as UBOP |
OPS |
Stored Beam & injection |
0815-0845 |
Check reboot effects on SCU6, SCU1 and HSCU |
Smith |
Stored beam |
0830-1700 |
Install conditioning structure at L5 |
RF, MOM |
Access Linac |
0830-0930 |
Reboot iocbramp |
Fors |
No Injection |
0845-1700 |
Cable pull from 40 FB IOC rack 40-02 to Room A014 |
Erwin |
No impact |
0845-0945 |
Replace module in main MPS IOC (all 4 SR RF systems off), followed by validation |
M. Smith |
No Beam |
0845-1045 |
Swap older quad converters |
Ackley/Vargas |
No Beam |
0845-1045 |
Investigate S12C:BM |
Jordan |
No Beam |
0845-1045 |
Investigate S6C:V1 |
Puttkammer |
No Beam |
0845-1045 |
Test SR P0 signal |
DiMonte, Yao |
No Beam |
0930-1030 |
Verify flag locations |
Yao |
Access Booster |
1100-1300 |
Switch from backups to pumps 503, 511, 513 & 519 -- Bumpless (set P.S. in Sectors 4 thru 7, 12 thru 17 and 20 thru 23 to zero) Switch from backup pump to 405 (not bumpless) Shutdown P.S. in Sectors 40,1,2,3 and SR Septa) |
Wright |
No Beam |
1330-1430 |
Replace RF1 klystron garage blower (all five Bldg. 420 RF systems off) |
Wright |
No Beam |
1700-1730 |
Recover injectors, verify stored beam |
OPS |
Stored beam & injectors |
1730-2000 |
RTFB matrix modification for outputting to S40AH3 vacant channel. |
Emery, Carwardine |
Stored beam & injection |
2000-2400 |
Orbit Switch |
Xiao |
Stored beam & injection |
2200-2400 |
Booster orbit change at 6 GeV |
Emery |
Occasional injection possible |
|
Tuesday, March 1, 2018 |
|
|
2000-0100 |
Booster orbit change at 6 GeV |
Emery |
Occasional injection possible |
0100-0500 |
6 GeV SR lattice |
Emery, Xiao |
Stored beam & injection |
0530-0630 |
Test HSCU communications failure and recovery with beam |
M. Smith |
Stored beam |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |